To calculate the estimated annual payback period, a buyer will need to know the estimated annual savings made from implementing the option, and also the estimated costs.
Is this statement correct?
- A . Yes, the calculation will be the estimated total costs divided by the estimated annual savings
- B . No, the calculation will be the estimated total costs multiplied by twelve
- C . Yes, the calculation will be the estimated annual savings added to the estimated total costs
- D . No, the calculation will be the estimated annual savings multiplied by the rate of inflation
To calculate the estimated annual payback period, a buyer will need to know the estimated annual savings made from implementing the option, and also the estimated costs.
Is this statement correct?
- A . Yes, the calculation will be the estimated total costs divided by the estimated annual savings
- B . No, the calculation will be the estimated total costs multiplied by twelve
- C . Yes, the calculation will be the estimated annual savings added to the estimated total costs
- D . No, the calculation will be the estimated annual savings multiplied by the rate of inflation
OMK is a Russian steel firm that is expanding market abroad. It plans to build a steel plant in a foreign country. Due to intricate technical requirements, the plant design will be very complex. Procurement department or technical department alone cannot draft the specification. OMK senior management decides that this task must be treated as a project.
Which of the following should be done before writing the specification for new steel plant?
- A . Develop the performance framework for the supplier
- B . Draft the terms and conditions for plant construction contract
- C . Invite suppliers to the tendering process
- D . Develop project initial document
D
Explanation:
The writing of a complex specification should be treated as a project because it requires the brain power from different stakeholders. Many tools and processes of project management can be applied to complex specification development. Before engaging with the stakeholders and implementing the project, the project initial document should developed.
A Project Initiation Document (PID) is one of the most important components of project management, which forms the foundation for a company project. It is a reference point during the entire project, for the client as well as for the project team.
A PID bundles documentation into a logical reference work that collects all important information needed to start and run a project from a good foundation. After that, Project Initiation Document must be transferred to all stakeholders, including business sponsors.
This forms the basis for the project management. The documentation from which the PID is com-posed include the business case in which the project’s justification can be found, the communication plan and the project plan.
The PID is composed out of collected information and includes, among others, the following com-ponents:
– Project goal(s); what do you want to achieve with the project?
– Project size; how large is the project, how long does it take and how many people are involved?
– Project organisation; who are involved in the project, what are their tasks, responsibilities and authority?
– Limits and risks; what can cause a project to stagnate and are there risks related to the project?
– Stakeholders; who has a stake in the success of the project?
– Project checks and frame reporting; by carefully taking into account evaluation moments, it is clear to everyone what sample tests can be carried out during the process.
In addition, it is important that the Project Initiation Document also contains the following infor-mation:
– The background and occasion of the project, which together provide information about the con-text.
– The project organisational structure, which describes who has which management responsibility in the project.
– The project quality plan, describing who controls the quality of the products to be delivered and how it will take place.
– The total project planning, including the duration of all activities.
– The exception process, which describes how exceptions are dealt with and the steps of the escalation procedure.
– The risk log, including the measures that will be taken when there are unforeseen risks.
– The documentation structure of the project, in which the encoding and storage of all documents and products to be provided by the project has been recorded in advance.
Reference: – CIPS study guide page 148
– Project Initiation Document (PID), a project management tool | ToolsHero
LO 3, AC 3.3
OMK is a Russian steel firm that is expanding market abroad. It plans to build a steel plant in a foreign country. Due to intricate technical requirements, the plant design will be very complex. Procurement department or technical department alone cannot draft the specification. OMK senior management decides that this task must be treated as a project.
Which of the following should be done before writing the specification for new steel plant?
- A . Develop the performance framework for the supplier
- B . Draft the terms and conditions for plant construction contract
- C . Invite suppliers to the tendering process
- D . Develop project initial document
D
Explanation:
The writing of a complex specification should be treated as a project because it requires the brain power from different stakeholders. Many tools and processes of project management can be applied to complex specification development. Before engaging with the stakeholders and implementing the project, the project initial document should developed.
A Project Initiation Document (PID) is one of the most important components of project management, which forms the foundation for a company project. It is a reference point during the entire project, for the client as well as for the project team.
A PID bundles documentation into a logical reference work that collects all important information needed to start and run a project from a good foundation. After that, Project Initiation Document must be transferred to all stakeholders, including business sponsors.
This forms the basis for the project management. The documentation from which the PID is com-posed include the business case in which the project’s justification can be found, the communication plan and the project plan.
The PID is composed out of collected information and includes, among others, the following com-ponents:
– Project goal(s); what do you want to achieve with the project?
– Project size; how large is the project, how long does it take and how many people are involved?
– Project organisation; who are involved in the project, what are their tasks, responsibilities and authority?
– Limits and risks; what can cause a project to stagnate and are there risks related to the project?
– Stakeholders; who has a stake in the success of the project?
– Project checks and frame reporting; by carefully taking into account evaluation moments, it is clear to everyone what sample tests can be carried out during the process.
In addition, it is important that the Project Initiation Document also contains the following infor-mation:
– The background and occasion of the project, which together provide information about the con-text.
– The project organisational structure, which describes who has which management responsibility in the project.
– The project quality plan, describing who controls the quality of the products to be delivered and how it will take place.
– The total project planning, including the duration of all activities.
– The exception process, which describes how exceptions are dealt with and the steps of the escalation procedure.
– The risk log, including the measures that will be taken when there are unforeseen risks.
– The documentation structure of the project, in which the encoding and storage of all documents and products to be provided by the project has been recorded in advance.
Reference: – CIPS study guide page 148
– Project Initiation Document (PID), a project management tool | ToolsHero
LO 3, AC 3.3
Which of the following are typical benefits of through-life asset management to buying organization? Select the TWO that apply.
- A . Shorter specifications
- B . Lower risks as there are many suppliers accountable for costs and service over the life of the asset
- C . Lower total cost of ownership
- D . Greater supplier’s bargaining power
- E . Better capability of supplier over time
C, E
Explanation:
According to Andrew Graves, “Through-life Management involves the life-cycle management of the products, services and activities required to deliver a fully integrated capability to the customer, while reducing the cost of ownership for the customer.”
Benefits of through-life asset management can be:
– Lower total life-cycle costs
– Better match between the asset and end-user’s needs
– Better supplier capabilities over time because it gains experience of buying organisation’s needs.
Reference: CIPS study guide page 131
LO 3, AC 3.2
Which of the following are typical benefits of through-life asset management to buying organization? Select the TWO that apply.
- A . Shorter specifications
- B . Lower risks as there are many suppliers accountable for costs and service over the life of the asset
- C . Lower total cost of ownership
- D . Greater supplier’s bargaining power
- E . Better capability of supplier over time
C, E
Explanation:
According to Andrew Graves, “Through-life Management involves the life-cycle management of the products, services and activities required to deliver a fully integrated capability to the customer, while reducing the cost of ownership for the customer.”
Benefits of through-life asset management can be:
– Lower total life-cycle costs
– Better match between the asset and end-user’s needs
– Better supplier capabilities over time because it gains experience of buying organisation’s needs.
Reference: CIPS study guide page 131
LO 3, AC 3.2
Aircraft Category Manager, Harpal Patel, is purchasing several aircraft engines. He is seeking to determine which category of specification will be most appropriate. He decides on using a conformance-based specification.
A conformance-based specification is most appropriate in which one of the following instances?
- A . When technical dimensions are necessary for operational reasons
- B . When technology is changing rapidly in the market sector
- C . Where suppliers have greater relevant technical expertise than the buyer
- D . Where there are clear objective criteria for evaluating alternative solutions put forward by suppliers
XYZ Ltd is the largest consumer of brass in the country. It consumes 48% of all brass manufactured, while the second-largest consumes less than 10% of brass manufactured.
Which force or power does XYZ Ltd possess?
- A . Market rivalry force
- B . Threat of substitute force
- C . Buyer bargaining power
- D . Supplier bargaining power
A "modified re-buy" means …
- A . The existing specifications should be reviewed but not the supply market, as this type of purchase is complex
- B . The specification should not be considered for future treatment as a stock item because of the modification
- C . Both the specification and the market should be reviewed to manage the new circumstances
- D . The existing supplier should be asked to supply the requirement because it is a modified re-buy of the same item
After a project, the procurement team at CLK Ltd meets up and summarises on the performance. They see that they actually spent $5,000 less than planned budget. The team tries to identifies why there is such difference.
This activity is known as…?
- A . Cash flow analysis
- B . Variance analysis
- C . Rolling budget
- D . Cost modelling
B
Explanation:
The procurement team in the scenario is analysing the difference between the plan and actual spend. This activity is known as variance analysis. The sum of all variances gives a picture of the overall over-performance or under-performance for a particular reporting period. For each item, companies assess their favorability by comparing actual costs to standard costs in the industry.
For example, if the actual cost is lower than the standard cost for raw materials, assuming the same volume of materials, it would lead to a favorable price variance (i.e., cost savings). However, if the standard quantity was 10,000 pieces of material and 15,000 pieces were required in production, this would be an unfavorable quantity variance because more materials were used than anticipated.
Reference: – CIPS study guide page 57-58- Variance Analysis – Learn How to Calculate and Analyze Variances (corporatefinanceinsti-tute.com) LO 1, AC 1.4