Which of the following can be used to calculate planned cost when creating a resource plan? Choose 2 answers
- A . Demand rate
- B . Rate card
- C . Default rate
- D . Project rate
BD
Explanation:
According to the ServiceNow documentation1, a rate card is a table that defines the hourly cost of labor for different roles or resources. A project rate is a fixed rate that is applied to all resources assigned to a project, regardless of their roles or individual rates. Both of these can be used to calculate the planned cost of a resource plan by multiplying the hours allocated to each resource by the corresponding rate.
The other options are incorrect because:
A) Demand rate: A demand rate is a rate that is applied to a demand, not a resource plan. It is used to estimate the cost of fulfilling a demand before it is converted into a project2.
C) Default rate: A default rate is a rate that is applied to a resource when no other rate is specified. It is not a valid option for calculating the planned cost of a resource plan, as it is only used as a fallback option3.
1: https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/resource-management/concept/c_RateCards.html
2: https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/concept/c_DemandRate.html
3: https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/resource-management/concept/c_DefaultRate.html
Demand assessments are triggered as soon as the demand enters what state?
- A . Approved.
- B . Screening.
- C . Qualified.
- D . Submitted.
D
Explanation:
According to the Completing Demand Assessments document, demand assessments are triggered as
soon as the demand enters the Submitted state. The other options are not correct, as demand assessments are not triggered when the demand is Approved, Screening, or Qualified.
A user’s availability is calculated as:
- A . Allocated time
- B . Capacity minus allocation
- C . Sum of allocated and confirmed hours, divided by the total capacity
- D . Allocated hours divided by the total capacity
D
Explanation:
According to the ServiceNow documentation1, a user’s availability is calculated as the ratio of allocated hours to total capacity, expressed as a percentage. Allocated hours are the hours that a user is assigned to work on a project or demand. Total capacity is the maximum number of hours that a user can work in a given period, based on their schedule and availability profile. A user’s availability indicates how much of their time is already allocated and how much is still available for new assignments.
1: https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/resource-management/concept/c_ResourceManagement.html
The project property to update actual effort from time card is controlled at what level?
- A . Application Level (Global).
- B . Portfolio Level.
- C . Program Level.
- D . Project Level.
D
Explanation:
According to the ServiceNow documentation1, the project property to update actual effort from time card is controlled at the project level. This property is called Update actual effort from time card and it determines if the Actual effort field on the Dates tab should be updated based on the hours entered from time cards for the project. If set to Yes, the Actual effort field is read-only on the Project and Project Task forms. If set to No, the Actual effort field is editable on the Project and Project Task forms.
1: https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-management/reference/r_Properties.html
Which plugin activates the Ideas module to gather and evaluate ideas efficiently, and quickly identify ideas for implementation?
- A . Test Management 2.0
- B . Agile Development 2.0
- C . Ideation with PPM
- D . Resource Management
C
Explanation:
According to the Innovation Management document, the plugin that activates the Ideas module to gather and evaluate ideas efficiently, and quickly identify ideas for implementation is Ideation with PPM. This plugin enables the Innovation Management application, which allows organizations and employees to collect, vote on, manage, and collaborate on ideas from a centralized location. The other options are not correct, as they are not plugins that activate the Ideas module. Test Management 2.0 is a plugin that enables the Test Management 2.0 application, which allows users to create, plan, and execute tests. Agile Development 2.0 is a plugin that enables the Agile Development 2.0 application, which allows users to manage scrum or development work throughout the lifecycle. Resource Management is a plugin that enables the Resource Management application, which allows users to manage resource plans and allocations.
Which role is needed to group related projects and demands?
- A . it_program_manager
- B . it_project_manager
- C . it_demand_manager
- D . it_project_user
A
Explanation:
According to the ServiceNow documentation1, the it_program_manager role is needed to group related projects and demands. This role can create and manage programs, which are containers for projects and demands that share a common goal or objective.
The other options are incorrect because:
B) it_project_manager: The it_project_manager role can create and manage projects, but not group them into programs2.
C) it_demand_manager: The it_demand_manager role can create and manage demands, but not group them into programs3.
D) it_project_user: The it_project_user role can view and edit project tasks, but not create or manage projects, demands, or programs4.
1: https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-portfolio-management/concept/c_ProgramManagement.html
2: https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-management/concept/c_ProjectManagement.html
3: https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/concept/c_DemandManagement.html
4: https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-management/reference/r_Roles.html
The RIDAC workflow can be modified by using which recommended feature?
- A . Workflow Editor
- B . Project Form
- C . Flow Designer
- D . Service Catalog
A
Explanation:
According to the RIDAC (Risk, Issue, Decision, Action, and Request Changes) record entries for a project document, the RIDAC workflow can be modified by using the Workflow Editor, which is a graphical tool that allows you to create and edit workflows. The other options are not correct, as they are not recommended features for modifying the RIDAC workflow. The Project Form is used to create and update project records. The Flow Designer is used to automate processes without coding. The Service Catalog is used to order items and services.
The Project management application supports two types of external dependencies.
What are they? Choose 2 answers
- A . Hard Dependency.
- B . Task Dependency.
- C . Change Dependency.
- D . Soft Dependency.
- E . Milestone Dependency.
AD
Explanation:
The Project Management application supports two types of external dependencies: hard dependency and soft dependency. A hard dependency is a dependency that must be met before a task can start or finish. A soft dependency is a dependency that is preferred but not mandatory for a task to start or finish. You can find more information about these dependency types in the Product Documentation for ServiceNow.
What information are users required to enter on a cost plan for a demand?
- A . Cost type
- B . Discount Rate %
- C . Total planned cost
- D . Functional currency
A
Explanation:
According to the Cost plan breakdown document, users are required to enter the cost type for each cost plan line item. Cost type is a mandatory field that specifies the type of cost, such as labor, software, hardware, etc. The other options are not required fields for a cost plan for a demand. Discount Rate % is an optional field that applies a discount rate to the cost plan. Total planned cost is a read-only field that displays the sum of the planned cost for all the cost plan breakdowns. Functional currency is a system property that defines the currency used for cost management.
A project expense line is cost associated with a specific source, except for:
- A . Fixed Assets.
- B . Program.
- C . Resource.
- D . Software.
B
Explanation:
According to the Project Expense Lines document, a project expense line is cost associated with a specific source, such as fixed assets, resource, or software. The program field on the project expense line form is not a source of cost, but a reference to the program that the project belongs to. Therefore, the correct answer is B. Program. The other options are not correct, as they are sources of cost for a project expense line.