If the ‘Move project for WIP projects’ property is enabled, project tasks associated with the project are also moved, except for tasks in which of the following states? Choose 2 answers
- A . Pending
- B . Work in Progress
- C . Closed
- D . Open
BC
Explanation:
According to the Planning Console document, if the ‘Move project for WIP projects’ property is enabled, project tasks associated with the project are also moved, except for tasks in the Work in Progress or Closed states. The other options are not correct, as tasks in the Pending or Open states are moved along with the project.
On the demand form, what does the Discount Rate impact?
- A . ROI.
- B . Net Present Value (NPV).
- C . Financial Benefit.
- D . Internal Rate of Return %.
B
Explanation:
According to the ServiceNow documentation1, the discount rate on the demand form impacts the net present value (NPV) of the demand. The NPV is the difference between the present value of the benefits and the present value of the costs of the demand. The discount rate is the rate used to discount future cash flows to their present value. A higher discount rate means that future cash flows are worth less in the present, and vice versa.
The other options are incorrect because:
A) ROI: The ROI (return on investment) is the ratio of the net value to the estimated cost of the demand. The discount rate does not affect the ROI, as both the net value and the estimated cost are based on the present value of the cash flows2.
C) Financial Benefit: The financial benefit is the sum of the present value of the benefits of the demand. The discount rate does not affect the financial benefit directly, but only indirectly through the NPV calculation3.
D) Internal Rate of Return %: The internal rate of return % (IRR) is the discount rate that makes the NPV of the demand equal to zero. The discount rate does not affect the IRR, but rather the IRR is derived from the NPV equation4.
1: https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/reference/r_DemandTable.html
2: https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/concept/c_DemandRate.html
3: https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/concept/c_FinancialBenefit.html
4: https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/concept/c_InternalRateOfReturn.html
What is a resource event?
- A . An external event.
- B . A non-scheduled activity impacting capacity.
- C . A block of time that a resource spends on a task.
- D . An event scheduled by a project manager.
B
Explanation:
A resource event is a non-scheduled activity that affects the availability and capacity of a resource or a group of resources. Examples of resource events are vacations, holidays, training, or sick leave. Resource events can be created by resource managers or resources themselves, and they can be viewed in the resource calendar or the resource workbench. You can find more information about resource events in the Product Documentation for ServiceNow.
If a user creates a new demand from the demand workbench, what state will the system save the record in?
- A . approved
- B . open
- C . draft
- D . qualified
D
Explanation:
According to the Using the Demand Workbench document, if a user creates a new demand from the demand workbench, the system saves the record in the qualified state and displays it on the bubble chart. The other options are not correct, as they are not the default state for a new demand created from the demand workbench. The approved state is the final state for a demand that has passed all the assessments. The open state is the initial state for a demand that is created from the Service Catalog. The draft state is the state for a demand that is created from the Demand form.
What is the first step in the process when configuring Portfolio Planning to work with ServiceNow® Project Portfolio Management?
- A . Create an alignment integration.
- B . Create custom mapping configurations.
- C . Generate default mapping configurations.
- D . Create personalized portfolio plans.
C
Explanation:
According to the Portfolio Planning document, the first step in the process when configuring Portfolio Planning to work with ServiceNow® Project Portfolio Management is to generate default mapping configurations. This step creates the default mappings between the Portfolio Planning fields and the ServiceNow® Project Portfolio Management fields. The other options are not correct, as they are not the first step in the process. Creating an alignment integration is the second step, creating custom mapping configurations is the third step, and creating personalized portfolio plans is the fourth step.
If an it_project_manager does not want to equally distribute hours across the resource plan time frame, what allocation spread should be used?
- A . Even.
- B . Any.
- C . Back Load.
- D . Front Load.
B
Explanation:
If an it_project_manager does not want to equally distribute hours across the resource plan time frame, the allocation spread should be set to Any. This option allows the it_project_manager to manually enter the hours for each month or quarter in the resource plan. The other options (Even, Back Load, and Front Load) automatically distribute the hours evenly, from the end, or from the start of the time frame, respectively. You can find more information about the allocation spread in the Product Documentation for ServiceNow.
Which property controls the changes in cost and resource plans with respect to the change in the start date of a demand or project?
- A . ‘Change Resource Plan, Cost Plan and Benefit Plan Start Date with Demand or Project Start Date Change’.
- B . ‘Enable altering of planned date for task in WIP/Closed’.
- C . ‘Rollup project start date from tasks’.
- D . ‘Calculate ROI percentage based on a project’s estimated cost and its net value’.
A
Explanation:
According to the ServiceNow documentation1, this property controls whether the start dates of the resource plan, cost plan, and benefit plan are automatically updated when the start date of the demand or project is changed. If this property is set to true, then the plans will be shifted by the same number of days as the demand or project start date change. If this property is set to false, then the plans will not be affected by the demand or project start date change.
1: https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-management/reference/r_Properties.html
Which demand category would a demand manager select, if they need to create an enhancement?
- A . Defect
- B . Change
- C . Operational
- D . Strategic
C
Explanation:
What role can configure the default columns in the project planning console?
Choose 2 answers
- A . it_pps_admin
- B . it_project_manager
- C . it_console_admin
- D . admin
AD
Explanation:
According to the ServiceNow support article1, the it_pps_admin role can configure the default columns in the project planning console by modifying the pm_project_planning_console list view. The admin role can also do this, as well as any other configuration on the platform2.
1: https://support.servicenow.com/kb?id=kb_article_view&sysparm_article=KB0714565 2: https://docs.servicenow.com/bundle/vancouver-platform-administration/page/administer/users-and-groups/concept/c_Roles.html
When creating a project from demand, what related records are moved and copied upon Project Creation?
- A . Resource Plan and Cost Plan.
- B . Resource Plan and Change Requests.
- C . Idea and Demand.
- D . Cost Plan and Assessment.
A
Explanation:
According to the Create a customer project from a demand document, when creating a project from demand, the resource plan and the cost plan are moved and copied upon project creation. The resource plan defines the resources required for the project, and the cost plan defines the estimated and actual costs for the project. The other options are not correct, as they are not related records that are moved and copied upon project creation. The change requests, the idea, and the demand are not moved or copied to the project, but they are linked to the project as references. The assessment is not a record that is associated with the project, but with the demand.