An architect is tasked with devising a vSphere design strategy that will allow the company to quickly scale global data center functionality when a new location is identified.
The following requirements must be met:
The solution must include VMware licensing costs.
The design must keep data locally to each specific location.
The design must utilize current company processes around vSphere.
Any new global location must be functional within one month of identification.
Which design strategy will meet these requirements?
- A . Plan specific locations throughout the world and build data centers in anticipation of the scale events.
- B . Purchase new hardware and deploy VMware Cloud Foundation when a new location is identified.
- C . Select partners in each identified location in anticipation of the scale events.
- D . Locate a partner that has a data center presence in major global locations that can deploy compatible company architecture.
An architect is designing a new vSphere architecture and notes the following information during the design workshops:
vSphere distributed switches (VDS) will be used for all vSphere clusters. Switch naming will be based on cluster name, resource type function and switch number.
Port group naming will be based on function, role and VLAN number range.
Each host has two physical network cards each with two NIC ports:
– Card A aligns to vmnic0 and vmnic1
– Card B aligns to vmnic2 and vmnic3
The architecture must provide resilient network connections.
Management Services will use VLAN ID 43.
Virtual machines access VLAN ID 100.
The vSphere infrastructure will use a hyper-converged storage architecture.
How should the architect document the VDS physical design based on the noted information?
- A . – vSwitch Prod_DVS_01 will have 2 uplinks
– Port group name "pg_mgmt_43"
– uplink = vmnic0
– teaming policy = active/passive
– Port group name "pg_VM_100"
– uplink = vmnic1
– teaming policy = active/passive - B . vSwitch Prod_DVS_01 will have 4 uplinks
Port group name "pg_mgmt_43"
– uplink = vmnic0, vmnic2
– teaming policy = active/passive
Port group name "pg_VM_100"
– uplink = vmnic1, vmnic3
– teaming policy = active/passive - C . – vSwitch Prod_DVS_01 will have 4 uplinks
– Port group name "pg_mgmt_43"
– uplink = vmnic0, vmnic1
– teaming policy = active/passive
– Port group name "pg_VM_100"
– uplink = vmnic2, vmnic3
– teaming policy = active/passive - D . – vSwitch Prod_DVS_01 will have 4 uplinks
– Port group name "pg_mgmt"
– uplink = vmnic0, vmnic2
– teaming policy = active/passive
– Port group name "pg_VM"
– uplink = vmnic1, vmnic3
– teaming policy = active/passive
An architect is documenting the design for a new multi-site vSphere solution. The customer has informed the architect that the workloads hosted on the solution are managed by application teams who must perform a number of steps to return the application to service following a failover of the workloads to the secondary site. These steps are defined as the Work Recovery Time (WRT). The customer has provided the architect with the following information about the workloads, including the recovery time objective (RTO) and recovery point objective (RPO):
Critical workloads have a WRT of 12 hours
Production workloads have a WRT of 24 hours
Development workloads have a WRT of 24 hours
All workloads have an RPO of 4 hours
Critical workloads have an RTO of 1 hour
Production workloads have an RTO of 12 hours
Development workloads have an RTO of 24 hours
The customer has also confirmed that production and development workloads are managed by the same team and the disaster recovery solution will not begin the recovery of the development workloads until all critical and production workloads have been recovered at the secondary site.
Which three statements would the architect document as the maximum tolerable downtime (MTD)
for workloads within the design? (Choose three.)
- A . Critical Workloads: 12 hours
- B . Development Workloads: 24 hours
- C . Production Workloads: 36 hours
- D . Critical Workloads: 13 hours
- E . Development Workloads: 60 hours
- F . Production Workloads: 24 hours
Following a review of security requirements, an architect has confirmed the following requirements:
– REQ001- A clustered firewall solution must be placed at the perimeter of the hosting platform, and all ingress and egress network traffic will route via this device.
– REQ002- A distributed firewall solution must secure traffic for all virtualized workloads.
– REQ003- All virtualized workload, hypervisor, firewall and any management component system events must be monitored by security administrators.
– REQ004- The hosting platforms security information and event management (SIEM) system must be scalable to 20,000 events per second.
– REQ005- The hosting platforms storage must be configured with data-at-rest encryption.
– REQ006- The hosting platform limits access to authorized users.
Which three requirements would be classified as technical (formerly non-functional) requirements? (Choose three.)
- A . A clustered firewall solution must be placed at the perimeter of the hosting platform, and all ingress and egress network traffic will route via this device.
- B . A distributed firewall solution must secure traffic for all virtualized workloads.
- C . The hosting platforms security information and event management (SIEM) system must be scalable to 20,000 events per second.
- D . The hosting platforms storage must be configured with data-at-rest encryption.
- E . The hosting platform limits access to authorized users.
- F . All virtualized workload, hypervisor, firewall and any management component system events must be monitored by security administrators.
An architect is tasked with designing a solution to monitor the operational state of a VMware Cloud Foundation environment through ad-hoc reporting and custom dashboards, alerts, and notifications.
Using VMware Validated Solutions, which validated solution can the architect leverage to meet this requirement?
- A . Private Cloud Automation for VMware Cloud Foundation
- B . Intelligent Operations Management for VMware Cloud Foundation
- C . VMware Validated Design for VMware Cloud Foundation Heath Reporting and Monitoring for VMware Cloud Foundation