Question #271
A design team is working on a hospital project.
In order to meet the Energy and Atmosphere Prerequisite, Minimum Energy Performance, what option is used?
- A . Whole building simulation
- B . EPA target finder rating tool
- C . Green-e Energy
- D . Advanced building core performance guide
Correct Answer: A
A
Explanation:
The Whole Building Simulation option is used to meet the Energy and Atmosphere Prerequisite, Minimum Energy Performance for a hospital project. This option involves creating a detailed computer model of the building to simulate its energy performance and identify opportunities for improvement.
Reference: LEED AP Building Design + Construction (LEED AP BD+C) V4 resources 1
A
Explanation:
The Whole Building Simulation option is used to meet the Energy and Atmosphere Prerequisite, Minimum Energy Performance for a hospital project. This option involves creating a detailed computer model of the building to simulate its energy performance and identify opportunities for improvement.