Complete the sentence. According to the TOGAF standard, an ___________ is a representation of a system from the perspective of a related set of _______________.
- A . architecture view, stakeholders
- B . architecture viewpoint, stakeholders
- C . architecture viewpoint, architecture views
- D . architecture view, requirements
- E . architecture view, concerns
A
Explanation:
Reference: https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap03.html
Which of the following describes a key objective of the Technology Architecture Phase?
- A . To define the solution architecture needed to support the Application Architecture
- B . To define technology components into a set of technology platforms
- C . To define the Transition Architectures needed to achieve the Target Architecture
- D . To develop a migration plan to deliver incremental capabilities
- E . To select a set of technology products that will form the basis of a solution architecture
What data will need to be shared?
At present, there are no particularly useful architectural assets related to this initiative, so all assets need to be acquired and customized or created from scratch. The company prefers to implement existing package applications from systems vendors with little customization.
The architecture development project has just completed its Architecture Context iteration cycle and is about to begin the Architecture Definition iteration cycle. The company is using TOGAF for its internal Enterprise Architecture activities. It uses an iterative approach for executing Architecture Development Method (ADM) projects.
The architecture development project has just completed its Architecture Context iteration cycle and is about to begin the Architecture Definition iteration cycle.
Refer to the Scenario.
You are serving as the Lead Architect.
You have been asked to identify the most appropriate architecture viewpoints for this situation.
Based on TOGAF 9, which of the following is the best answer?
- A . In the early iterations of the Architecture Definition:Describe the Baseline Business Architecture with a Baseline Business Process catalogDescribe the Baseline Application Architecture with a Technology Portfolio catalogDescribe the Baseline Data Architecture with a Data diagramIn the later iterations of the Architecture Definition:Describe the Target Business Architecture with an Actor/Process/Data catalogDescribe the Target Application Architecture with a System/Technology matrixDescribe the Target Data Architecture with a Data Dissemination diagram
- B . In the early iterations of the Architecture Definition:Describe the Target Business Architecture with a Business Service/Function catalog and a Business Interaction matrixDescribe the key business objects with Product Lifecycle diagramsDescribe the Target Application Architecture with Application Communication diagrams and an Application Interaction matrixDescribe the Target Data Architecture with a Data Entity/business Function matrix and a System/Data matrixIn the later iterations of the Architecture Definition:Describe the Baseline Business Architecture with a Business Service/Function catalog and a Business Interaction matrixDescribe the Baseline Application Architecture with a System/Organization matrix and a System/function matrixDescribe the Baseline Data Architecture with a Data Entity/Data Component catalog
- C . In the early iterations of the Architecture Definition:Describe the Target Business Architecture with a Business Service/Function catalog and an Organization/Actor catalogDescribe the key business objects with Data Lifecycle diagramsDescribe the Target Application Architecture with Application Communication diagrams and an Application Interaction matrixDescribe the Target Data Architecture with a System/Data matrixIn the later iterations of the Architecture Definition:Describe the Baseline Business Architecture with a Business Service/Function catalog and a Business Interaction matrixDescribe the Baseline Application Architecture with an Application and User Location diagram and a System/Function matrixDescribe the Baseline Data Architecture with a Data Entity/Data Component catalog
- D . In the early iterations of the Architecture Definition:Describe the Baseline Business Architecture with an Organization/Actor catalogDescribe the Baseline Application Architecture with a System/Function matrixDescribe the Baseline Data Architecture using a Data Entity/Data Component catalogIn the later iterations of the Architecture Definition:Describe the Target Business Architecture with an Organization/Actor catalogDescribe the Target Application Architecture using Application Communication diagrams and an Application Interaction matrixDescribe the Target Data Architecture with a System/Data matrix
In which phase of the ADM cycle do building blocks become implementation-specific?
- A . Phase A
- B . Phase B
- C . Phase C
- D . Phase D
- E . Phase E
Please read this scenario prior to answering the question
Your role is that of an Enterprise Architect at an multinational company. The company designs, manufactures and sells products worldwide. It has grown rapidly by acquisition and has inherited numerous different business processes and related IT systems. This has led in many instances to a duplication of resources.
The Chief Operating Officer (COO) has made the decision to consolidate and reduce redundant business processes and IT systems in the sales operations. She has committed to the CEO that the business will migrate to a set of standardized solutions that will reduce costs and improve efficiency.
The Enterprise Architecture practice at the company has been assigned to manage the project. At present, there are no architectural assets in the Architecture Repository related to this initiative. All assets will need to be acquired, customized, or created from scratch. The CIO, who is the project sponsor, has identified the need for a set of commercial off the shelf package applications as candidates for the target. She has also stated that she is not concerned about preserving the existing business processes or IT systems within the sales operations.
Your team leader has asked you to assist with developing a response to the following questions:
Which groups of users will use the different applications and IT systems?
How many licenses and type of licenses are needed for the packaged applications?
What level of support is needed for the users?
Where should the support center(s) be located?
What new capabilities will be required to support this business change?
How much will the migration cost?
This project is using an iterative approach for executing the TOGAF Architecture Development Method. The architecture development project has completed the Architecture Vision Phase. A set of packaged applications has been identified and is being considered, the next iteration will include development of the Business and Application Target Architectures.
Refer the Scenario.
[Note: You may need to refer to the Architectural Artifacts chapter, section 31.6 (located in Part IV) of the reference text in order to answer this question.]
You have been asked to identify the most appropriate catalogs, matrices, and diagrams to support the Architecture development.
Based on the TOGAF Standard, Version 9.2, which of the following is the best answer?
- A . You would describe the Target Business Architecture with a Business Interaction matrix, and a Business Service/Function catalog. You would describe the Target Application Architecture with an Application Communication diagram, an Application Interaction matrix and an Interface catalog.
- B . You would describe the Target Business Architecture with an Organization/Actor catalog, a Business Service/Function catalog, and a Capability/Organization matrix. You would describe the Target Application Architecture with an Application Portfolio catalog and an Application/Function matrix.
- C . You would describe the Target Business Architecture with a Business Capability Map, a Location catalog, and an Organization/Actor catalog. You would describe the Target Application Architecture with an Application/Organization Matrix, and Application Migration diagram.
- D . You would describe the Target Business Architecture with a Business Service/Function catalog, a Location catalog, and an Organization/Actor catalog. You would describe the Target Application Architecture with an Application Migration diagram, and an Application and User Location diagram.
B
Explanation:
Analysis of Scenario and TOGAF Guidance
Given the scenario, the main objective is to create a consolidated and standardized architecture for sales operations using the TOGAF Architecture Development Method (ADM). The COO aims to reduce redundancy and enhance efficiency, while the CIO has specified a preference for off-the-shelf applications rather than preserving the current, potentially redundant systems.
The ADM process is currently transitioning from the Architecture Vision phase to the Business and Application Target Architectures in the next iteration. The identified areas of focus include defining the Target Business and Application Architectures, which require specific catalogs, matrices, and diagrams for effective representation.
Requirement: Selection of Artifacts
According to TOGAF 9.2, artifacts like catalogs, matrices, and diagrams are essential in representing different aspects of the architecture. These are detailed in Section 31.6 (Architectural Artifacts chapter, Part IV) of the TOGAF Standard, which outlines the purpose of each artifact type within the ADM phases.
Rationale for Option B
Target Business Architecture Artifacts:
Organization/Actor Catalog: This catalog is used to capture all actors (people, organizations, etc.) involved in the business operations. It is essential for mapping the current and target structure and aligns with the goal of consolidating operations to reduce redundancy.
Business Service/Function Catalog: This catalog lists all the business services and functions, helping identify which services/functions will remain, be removed, or be merged. This aligns with the objective of standardizing and streamlining processes.
Capability/Organization Matrix: This matrix maps business capabilities to organizational units, which helps define what new capabilities may be required to support the business change as requested by the COO.
Target Application Architecture Artifacts:
Application Portfolio Catalog: This catalog identifies and details applications involved in the target architecture, including the new off-the-shelf package applications. It is crucial for cataloging all software solutions that will be part of the consolidated system.
Application/Function Matrix: This matrix links applications to the business functions they support, which is instrumental in assessing how the new applications align with the business needs. Alignment with TOGAF ADM Guidelines ADM Phase B (Business Architecture): Catalogs like the Organization/Actor catalog and Business Service/Function catalog are appropriate to capture actors and their interactions with services. Additionally, matrices like the Capability/Organization matrix align with TOGAF guidelines to document necessary business capabilities and organizational responsibilities.
ADM Phase C (Application Architecture): For the Application Architecture, an Application Portfolio catalog supports cataloging applications as the organization considers packaged solutions. The Application/Function matrix is useful for mapping how these applications fulfill specific business functions, aligning with TOGAF guidance for this phase.
Why Options A, C, and D are Less Suitable
Option A: While it includes the Business Service/Function catalog, it does not provide sufficient emphasis on organizational structure or capabilities (e.g., Capability/Organization matrix), both of which are crucial for understanding the roles and responsibilities in the target business structure. Option C: This option suggests a Business Capability Map and Application/Organization matrix, which are less directly relevant to the immediate needs of cataloging applications and mapping functions to applications as specified by the CIO’s intent to move to standardized packages.
Option D: The Application Migration diagram and Application and User Location diagram are more appropriate for later stages of the architecture, focusing on implementation rather than the Business and Application Architectures, making them premature for this stage. TOGAF Reference Supporting Option B
Which of the following does the TOGAF ADM recommend for use in developing the Architecture Vision document?
- A . Architecture Principles
- B . Business Scenarios
- C . Interoperability Analysis
- D . Migration Planning Techniques
- E . Risk Management Techniques
Complete the sentence. The TOGAF standard covers the development of four architecture domains.
Application, Data, _________________.
- A . Business and Technology
- B . Information and Knowledge
- C . Baseline and Transition
- D . Vision and Requirements
- E . Capability and Segment
A
Explanation:
Reference: https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap06.html
Gap Analysis is a technique used in Phases B, C, D and E.
Which one of the following statements best describes the gap analysis technique?
- A . It highlights areas of stakeholder concern
- B . It highlights the impacts of change
- C . It highlights services that are yet to be developed
- D . It highlights services that are available
- E . It highlights different viewpoints
What are the four dimensions used to scope an architecture?
- A . Strategy, Portfolio, Project, Solution Delivery
- B . Strategy, Segment, Capability, Budget
- C . Business, Data, Application, Technology
- D . Breadth. Depth, Time Period, Architecture Domains
Complete the sentence. The Requirements Management Phase _____________________.
- A . addresses and resolves requirements between ADM phases
- B . is a central process that prioritizes requirements for all ADM phases
- C . is used to dispose of resolved requirements for all ADM phases
- D . generates new requirements and passes them to all ADM phases
- E . stores requirements and manages their flow into relevant ADM phases