The Open Group OG0-093 Practice Exams
Last updated on Oct 21,2026- Exam Code: OG0-093
- Exam Name: TOGAF 9 Combined Part 1 and Part 2
- Certification Provider: The Open Group
- Latest update: Oct 21,2026
Complete the sentence. In the Preliminary Phase, all of the following are part of preparing the organization to undertake successful enterprise architecture, except __________.
- A . defining architecture principles
- B . defining relationships between management frameworks
- C . defining the enterprise
- D . evaluating the enterprise architecture maturity
- E . identifying stakeholders and their concerns
Which phase of the ADM ensures that implementation projects conform to the defined architecture?
- A . Requirements Management
- B . Phase D
- C . Phase F
- D . Phase G
- E . Phase H
According to TOGAF, in which phase of the ADM should an initial assessment of business transformation readiness occur?
- A . Preliminary Phase
- B . Phase A
- C . Phase B
- D . Phase F
- E . Phase G
Which ADM phase establishes the connection between the architecture organization and the implementation organization through the Architecture Contract?
- A . Phase E
- B . Phase F
- C . Phase G
- D . Phase H
- E . Requirements Management
Which ADM phase defines the scope for the architecture development initiative and obtains approval to proceed with the architecture development?
- A . Phase D: Technology Architecture
- B . Phase A: Architecture Vision
- C . Requirements Management
- D . Phase B: Business Architecture
- E . Preliminary Phase
B
Explanation:
Reference: https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap06.html
Which of the following identifies business units that possess capabilities, and which participate in value streams?
- A . Business Capability Map
- B . Value Stream Map
- C . Organization Map
- D . Information Map
NO: 346
Scenario:
Please read this scenario prior to answering the question
Your role is that of a consultant to the Lead Enterprise Architect in a company that speicializes in luxury electric cars and their powertrain components, and also produces battery-charging equipment. It has its own distribution network, its own showrooms, and sells directly to customers via the internet. The company has four manufacturing facilities, two in the North America, one in Europe, and one in Asia.
A challenge that the company is facing to scale up the number of vehicles coming off the production line to meed customer demand, while maintaining quality. At the moment there are supply chain storages for key electronic components related to the autonomous drive system. In response the this, the research arm of the company has pioneered the development of a new self-driving platform. This new design uses common off-the-shelf components that will allow for a significant increase in overall vehicle production. This new design is ready to go into production.
The company has a mature Enterprise Architecture practice that is supported by a cross-functional Architecture Board. The TOGAF standard is used for developing the automated manufacturing process and systems used to design, manufacture and test the new design. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.
As part of putting the new self-driving platform into production, adjustments to the automated assembly processes need to be made. A pilot architecture project at a single location has defined an updated approach for controlling the automated test systems used to perform final quality assurance. The Chief Engineer, sponsor of the activity, and the Architecture Board have approved the plan for immediate implementation at each plant.
Architecture Contracts have been developed that detail the work needed to implement and deploy
the new automated test system controller for each location. The Chief Engineer has expressed concern that a uniform process be employed at each location to ensure consistency and quality.
Refer to the Scenario
The Lead Enterprise Architect has asked you to recommend the best approach to address the Chief Engineer’s concern.
Based on the TOGAF standard, which of the following is the best answer?
- A . You create an Architecture Contract to manage and govern the implementation and migration process. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contract. For internal development projects, you decide it is adequate to utilize a memorandum of understanding between the Architecture Board and the implementation organization. You recommend that if a deviation from the Architecture Contract is detected, the Architecture Board grant a dispensation to allow the implementation organization the ability to customize the process to meet their local needs.
- B . You use the Architecture Contracts to manage the architecture governance processes for the project across the locations. You deploy monitoring tools to assess the performance of each completed drive assembly at each location and develop change requirements if necessary. You recommend that if a deviation from the contract is detected, the Architecture Board should modify the Architecture Contract to allow the implementation organization the ability to customize the process to meet their local needs. As a result, you then issue a new Request for Architecture Work to implement the modified Architecture Definition.
- C . You create an Architecture Contract to manage and govern the implementation and migration process at each location. For internal development projects, you issue a memorandum of understanding between the Architecture Board and the implementation organization. For contracts issued to an external party, you ensure that it is a fully enforceable legal contract. You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
- D . You review the applicable Architecture Contract for each location, ensuring that it addresses the project objectives, effectiveness metrics, acceptance criteria, and risk management. In cases where the contract is issued to an external party, you ensure that it is a legally enforceable contract. You schedule compliance reviews at key points in the implementation process to ensure that the work is proceeding in accordance with the Architecture Definition. You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
What ADM phase defines the scope for the architecture development initiative and identifies the stakeholders?
- A . Requirements Management
- B . Preliminary Phase
- C . Phase B: Business Architecture
- D . Phase A: Architecture Vision
- E . Phase D: Technology Architecture
What class of architectural information within the Architecture Repository defines processes that support governance of the Architecture Repository?
- A . Architecture Capability
- B . Architecture Landscape
- C . Architecture Metamodel
- D . Governance Log
- E . Reference Library
In TOGAF, what is the difference between an artifact and a deliverable?
- A . An artifact contains one or more deliverables
- B . Artifacts and deliverables are synonymous; there is no difference between them
- C . Deliverables are prepared by the Project Manager, whereas artifacts are defined by the Architect
- D . Deliverables are reusable, whereas artifacts are unique to a given architecture project
- E . Deliverables are specified as contractual outputs from a project, whereas artifacts are not