What are personas?
- A . Descriptions of actual target customers or users
- B . Key end-users the Product Owner leverages for managing the backlog
- C . Fictional representations of target customers or users
Which two activities take place during Team Breakout #1 on the first day of Program In-crement (PI) Planning? (Choose two.)
- A . Risks on the teams’ planning boards are resolved by the Release Train Engineer
- B . Teams use color-coding for their backlog items as a reminder that they are re-quired to have all backlog item types on their planning boards
- C . Draft objectives and uncommitted objectives are written
- D . All teams’ planning boards are visible and use the same color-coding
- E . Draft objectives are written but do not include exploration Enablers
During Program Increment (PI) Planning, a scrum of scrums occurs just before the draft plan review. The Scrum Master from one team raises an issue that one of the Product Managers just showed up to the planning area with a priority wish list of items. These items do not align with the Feature prioritization.
What is the most likely planning anti-pattern causing this sudden impediment?
- A . There is strong alignment between business and marketing
- B . Planning decisions have been centralized
- C . Prioritization by Product Management was performed autonomously not collaboratively
- D . There is no social network that Solution development relies on
How does SAFe handle the ‘fear of conflict’ team dysfunction?
- A . Reviews results at the end of every iteration
- B . Avoids discussion of disagreements
- C . Has teams engage in retrospectives
- D . Uses scrum to create a safe environment for conflict
In the SAFe work item hierarchy, Features are decomposed into what?
- A . Stories
- B . Sub-Tasks
- C . Tasks
- D . Capabilities
What are two common PI Planning anti-patterns? (Choose two.)
- A . Stories are created for the Iterations
- B . The team decides which changes need to happen and when
- C . Too much time is spent analyzing each Story
- D . Scrum Masters who work with multiple teams do not have time for their teams
- E . Too much time is spent prioritizing Features
When should a Product Owner (PO) develop preliminary Iteration Goals?
- A . After PI Planning
- B . During PI Planning
- C . Prior to iteration planning
- D . During backlog refinement
Enabler Epics are used to advance what in order to support upcoming Business Epics?
- A . Value Stream(s)
- B . The Continuous Delivery Pipeline
- C . The Architectural Runway
How can a ReleaseTrain Engineer be aware of employee satisfaction?
- A . Gather employee Metrics immediately after the Agile Release Train launches
- B . Address and resolve any problems areas
- C . Conduct an employee Net Promoter Score survey
- D . Survey full-time employees
Who can the Release Train Engineer work with to help eliminate policies and procedures that demotivate employees?
- A . Business Owners
- B . Lean-Agile Leaders
- C . Portfolio Managers
- D . Product Management