Scrum SAFe Agilist 6.0 Practice Exams
Last updated on Oct 22,2026- Exam Code: SAFe Agilist 6.0
- Exam Name: SAFe 6 Agilist
- Certification Provider: Scrum
- Latest update: Oct 22,2026
Which statement is true about the Innovation and Planning (IP) Iteration?
- A . It is used annually when the team needs to refocus on work processes
- B . It is used as a weekly sync point between the Scrum Masters
- C . Without the IP Iteration, there is a risk that the ’tyranny of the urgent’ outweighs all innovation activities
- D . The Scrum Master can decide if the IP Iteration is necessary
What is the recommended frequency for updating Lean budget distribution?
- A . Every iteration
- B . Annually
- C . On demand
- D . Twice annually
Which SAFe Lean-Agile Principle includes the critical part of “delaying decisions to the last responsible moment”?
- A . Make value flow without interruptions
- B . Assume variability; preserve options
- C . Build incrementally with fast, integrated learning cycles
- D . Base milestones on objective evaluation of working systems
Which statement is true about batch size?
- A . Large batch sizes limit the ability to preserve options
- B . When stories are broken into tasks it means there are small batch sizes
- C . Large batch sizes ensure time for built-in quality
- D . When there is flow it means there are small batch sizes
Which statement is true when continuously deploying using a DevOps model?
- A . It alleviates the reliance on the skill sets of Agile teams
- B . It increases the transaction cost
- C . It lessens the severity and frequency of release failures
- D . It ensures that changes deployed to production are always immediately available to end-users
The Agile Release Train passes through four steps to deliver Solutions which include: defining new functionality, building, validating, and what else?
- A . Completing phase-gate steps
- B . Releasing
- C . Regulatory compliance
- D . DevOps testing
Who assigns business value (BV) to the team PI Objectives?
- A . Release Train Engineer
- B . Product Owner
- C . Business Owner
- D . Scrum Master
What is the biggest benefit of decentralized decision-making?
- A . Ensuring strategic decisions are not made in a vacuum
- B . Delivering value in the shortest sustainable lead time
- C . Creating better visualization
- D . Removing accountability from leaders
Which role serves as a servant leader for the Agile Release Train?
- A . Business Owner
- B . Release Train Engineer
- C . Agile Coach
- D . Scrum Master
When looking at an ART Planning Board, what does it mean when a feature is placed in a team’s swim lane with no strings?
- A . That the feature can be completed independently from the other teams
- B . That all the risks have been ROAMed
- C . That the team has little confidence it will happen
- D . That the feature should be completed before any other feature