You have several Scrum Teams are working on the same product.
What should be taken into consideration when Product Backlog items are distributed between the Scrum Teams?
Some criteria to consider are dependencies between items, teams, and the ability of a single team to deliver the item with minimal or no external help.
You have several Scrum Teams are working on the same product.
What should be taken into consideration when Product Backlog items are distributed between the Scrum Teams?
Some criteria to consider are dependencies between items, teams, and the ability of a single team to deliver the item with minimal or no external help.
As a Product Owner, why would it be important to have agility?
In what ways can a Product Owner influence agility?
Three examples how a Product Owner can influence agility:
As Scrum Teams mature, what is expected to happen? (Choose the best answer)
- A . Sprint Retrospectives will be less painful.
- B . The Sprint time-boxes will be shortened because the productivity is higher.
- C . Team membership will change in order to promote knowledge sharing.
- D . Their Definition of Done will expand to include more stringent criteria for higher quality.
- E . The Scrum Master becomes optional.
As Scrum Teams mature, what is expected to happen? (Choose the best answer)
- A . Sprint Retrospectives will be less painful.
- B . The Sprint time-boxes will be shortened because the productivity is higher.
- C . Team membership will change in order to promote knowledge sharing.
- D . Their Definition of Done will expand to include more stringent criteria for higher quality.
- E . The Scrum Master becomes optional.
Which statement best describes the Sprint Review? (Choose the best answer)
- A . An inspection of all of the work done in the Sprint by the Developers.
- B . An opportunity for the Scrum Team and stakeholders to inspect the Increment and collaborate on the next steps.
- C . A demonstration of functionality completed in the Sprint.
- D . An opportunity for the Product Owner to evaluate the results of the Developers.
Which of the following would be a topic at the Sprint Review? (Choose the best answer)
- A . The product Increment.
- B . How the Scrum process was followed during the Sprint.
- C . All of the above.
- D . Engineering and test practices.
Which statements are correct about the Sprint length? (Choose all that apply)
- A . Sprint length is decided at the Sprint Planning.
- B . It is best to have a consistent Sprint length throughout the development of the product.
- C . Sprints are 1 month or less.
- D . The length of the Sprint should be proportionate for designing, developing, and testing.
- E . Sprint length should only be based on the time to write the code.
Who’s responsible for engaging the stakeholders? (Choose the best answer)
- A . The Scrum Master
- B . The Developers
- C . The team leader
- D . The project manager
- E . The Product Owner
Who’s responsible for engaging the stakeholders? (Choose the best answer)
- A . The Scrum Master
- B . The Developers
- C . The team leader
- D . The project manager
- E . The Product Owner