When is the Sprint Backlog created? (Choose the best answer)
- A . During Product Backlog refinement.
- B . During Sprint Planning.
- C . Any time before Sprint Planning.
- D . At least one or two Sprints ahead.
To start the first Sprint, Scrum only needs enough solid ideas and a Scrum Team to implement those ideas.
True or False:
- A . False
- B . True
To start the first Sprint, Scrum only needs enough solid ideas and a Scrum Team to implement those ideas.
True or False:
- A . False
- B . True
In a highly competitive market, it is acceptable to release work that is not fully done if the Product Owner wants to be first to market.
True or False:
- A . True
- B . False
In a highly competitive market, it is acceptable to release work that is not fully done if the Product Owner wants to be first to market.
True or False:
- A . True
- B . False
What is the Product Owner’s responsibility during the Sprint Retrospective? (Choose the best answer)
- A . The Sprint Retrospective is only for the Developers.
- B . Gathering Product Backlog requirements.
- C . Deciding on process improvements for the Developers.
- D . Participating as a member of the Scrum Team.
As a Product Owner, what might you take into consideration when determining where an item belongs in the Product Backlog? (Choose all that apply)
- A . Alignment with the business strategy and goals.
- B . Dependencies with other Product Backlog Items.
- C . How important it is to customers.
- D . The techniques the Developers will apply to implement it.
- E . The level of risk.
What are appropriate responses if the Scrum Team identifies that the workload in the Sprint Backlog has become greater than their capacity during the Sprint Planning? (Choose the best two answers)
- A . The Scrum Team members ensure that the Product Owner is aware, starts the Sprint and monitors progress.
- B . Start the Sprint and add additional resources to the Scrum Team.
- C . Remove, replace, or make changes to selected Product Backlog items in the Sprint Backlog.
- D . Budget overtime in order to meet the commitment.
- E . Look for another team that has free capacity to take on the extra work.
A Scrum Team must have a Product Owner and Scrum Master.
True or False:
- A . True. Each must be a full-time member on the Scrum Team.
- B . False. If a Product Owner is unavailable, he/she can be replaced by a Business Analyst.
- C . False. A Scrum Master is only necessary when requested or needed.
- D . True. Their participation and availability will impact the outcomes produced by the Scrum Team.
A Scrum Team must have a Product Owner and Scrum Master.
True or False:
- A . True. Each must be a full-time member on the Scrum Team.
- B . False. If a Product Owner is unavailable, he/she can be replaced by a Business Analyst.
- C . False. A Scrum Master is only necessary when requested or needed.
- D . True. Their participation and availability will impact the outcomes produced by the Scrum Team.