Which statement describes the best way to learn from experiments? (choose the best answer)
- A . Running one experiment on the product that is open-ended is the best way to gather the most sufficient and accurate data.
- B . Running multiple experiments on the same product at the same time is the best way to reduce the cost of testing new ideas.
- C . Running multiple experiments on the same product at the same time is the best way to reduce the time and complexity of testing new ideas.
- D . Running one experiment on the product at a time is the best way for you to understand how the
results you observed affect your desired outcomes.
Which statement describes the best way to learn from experiments? (choose the best answer)
- A . Running one experiment on the product that is open-ended is the best way to gather the most sufficient and accurate data.
- B . Running multiple experiments on the same product at the same time is the best way to reduce the cost of testing new ideas.
- C . Running multiple experiments on the same product at the same time is the best way to reduce the time and complexity of testing new ideas.
- D . Running one experiment on the product at a time is the best way for you to understand how the
results you observed affect your desired outcomes.
Which of the following statements about the Product Backlog are true? (choose the best two answers)
- A . The Product Backlog should be visible to the Scrum Team and stakeholders.
- B . The Product Backlog represents the input of all stakeholders and eliminates any need for the Developers to speak to stakeholders.
- C . All Product Backlog items must be expressed as user stories
- D . The Product Backlog is ordered by the Product Owner
- E . Only the Product Owner can place items on the Product Backlog.
- F . All Product Backlog items must be identified before the first Sprint begins.
Which of the following would likely be the least effective way to enhance the agility of your future product development? (choose the least effective approach)
- A . Consider whether there is a significantly large enough market for your product.
- B . Form a holistic view of how the customer sees your product.
- C . Clearly understand the producer, buyer/consumer relationship.
- D . Lean on your organizational efficiency and existing architecture to build your product aligned to the current organization.
What can be measures of internal value? (choose all that apply)
- A . Customer or user satisfaction gap
- B . Time spent context-switching
- C . Employee Satisfaction
- D . On-Product Index
- E . Cycle Time
Which two Key Value Areas are most affected by the daily frequency a team is switching tasks or is interrupted? (choose the best two answers)
- A . All of the above.
- B . Time to Market.
- C . Unrealized Value.
- D . Ability to Innovate.
- E . Current Value.
Conducting small experiments to validate concepts with customers provides valuable insights into the potential value of proposed solutions. However, the financial department at ABC company feels that the experiments are not cost-effective.
What is the appropriate response to the finance department? (choose the best answer)
- A . Experiments are only required in very limited circumstances as reviews by stakeholders can often achieve the same or better results.
- B . Experiments should not be run on products that are already launched because experiments are only effective for new products.
- C . Proposed solutions are likely to succeed as they are based on market research.
- D . It is more cost-effective to allocate a small sum of money to validate a solution than to create a
solution that does not meet the customer’s actual needs.
As an investor or shareholder, which of the following measures might give you insight about whether a product is delivering value? (Choose all that apply)
- A . The average selling price as compared to close competitors
- B . Revenue per Employee
- C . The weekly velocity of the Developers
- D . Market Share
- E . Product profitability
Tommy, a young and talented Product Owner, decided to release continuously new features. He supposed that more frequent releases increase the quality of the value.
What could be the potential problems with his releasing strategy? (choose ALL that apply).
- A . The end-users are confused and getting annoyed with the constant releases.
- B . There is no problem with Tommy’s releasing strategy.
- C . The stakeholders are unhappy because the budget is consumed too quickly
- D . The Developers notifies that technical debt is accumulating.
When should the Product Owner update the project plan? (choose the best answer)
- A . Before the Sprint Planning to know how much work will have to be done in the Sprint.
- B . Scrum forbids having a project plan.
- C . The Product Backlog is the plan in Scrum. It is updated as new information and insights emerge.
- D . After the Daily Scrum to ensure an accurate daily overview of project progress.