Question #21
Who must attend the Daily Scrum?
- A . The Scrum Master and Product Owner.
- B . The Development Team.
- C . The Development Team and Product Owner.
- D . The Scrum Team.
- E . The Development Team and Scrum Master.
Question #22
What is the recommended size for a Development Team?
- A . 7 plus or minus 3.
- B . At least 7.
- C . 9.
- D . 3 to 9.
Question #23
How is management external to the Scrum Team involved in the Daily Scrum?
- A . The Scrum Master speaks on their behalf.
- B . The Development Team self-manages and is the only management required at the Daily Scrum.
- C . Management gives an update at the start of each Daily Scrum.
- D . The Product Owner represents their opinions.
Question #24
What are three ways Scrum promotes self-organization? (Choose three.)
- A . By not allowing documentation.
- B . By the Development Team deciding what work to do in a Sprint.
- C . By preventing stakeholders from entering the development room.
- D . By removing titles for Development Team members.
- E . By being a lightweight framework.
Question #25
Which of these may a Development Team deliver at the end of a Sprint?
- A . Failing unit tests, to identify acceptance tests for the next Sprint.
- B . An increment of software with minor known bugs in it.
- C . An increment of working software that is “done”.
- D . A single document, if that is what the Scrum Master asked for.
Question #26
The Product Owner is not collaborating with the Development Team during the Sprint.
What are two valuable actions for a Scrum Master to take? (Choose two.)
- A . Inform the Product Owner’s functional manager.
- B . Stop the Sprint, send the Product Owner to a course and restart.
- C . Bring up the problem in the Sprint Retrospective.
- D . Coach the Product Owner in the values of Scrum and incremental delivery.
- E . Nominate a proxy Product Owner.
Question #27
Which of the following services are appropriate for a Scrum Master in regard to the Daily Scrum?
- A . Lead the discussions of the Development Team.
- B . Make sure that all 3 questions have been answered by each member of the team.
- C . Keep track of whether each team member has a chance to speak.
- D . Teach the Development Team to keep the Daily Scrum within the 15 minute time-box.
- E . All of the above.
Question #28
The length of a Sprint should be:
- A . Short enough to keep the business risk acceptable to the Product Owner.
- B . Short enough to be able to synchronize the development work with other business events.
- C . No more than one calendar month.
- D . All of these answers are correct.
Question #29
How much of the Sprint Backlog must be defined during the Sprint Planning event?
- A . Just enough tasks for the Scrum Master to be confident in the Development Team’s understanding of the Sprint.
- B . The entire Sprint Backlog must be identified and estimated by the end of the Sprint Planning meeting.
- C . Enough so the Development Team can create its best forecast of what is can do, and to start the first several days of the Sprint.
- D . Just enough to understand design and architectural implications.
Question #30
Who should make sure everyone on the Development Team does their tasks for the Sprint?
- A . The Project Manager.
- B . The Product Owner.
- C . The Scrum Master.
- D . The Development Team.
- E . All of the above.