Which of these are LEAST likely to be included in the definition of "Workflow" policies? (choose the best three answers)
- A . Definition of Done.
- B . Work Item types.
- C . Pull/prioritization policies.
- D . A Gantt chart.
- E . Service Level Expectations.
- F . The Increment.
- G . A Burndown chart.
- H . Visualization policies.
- I . WIP Limits.
Kanban for Scrum Teams is built upon which Scrum Values? (choose the best three answers)
- A . Focus
- B . Transparency
- C . Professionalism
- D . Courage
- E . Openness
What might be discussed during the Sprint Retrospective if the Scrum Team is considering to use Kanban to complement their Scrum? (choose the best answer)
- A . Workflows.
- B . Current policies.
- C . Work in Progress (WIP) Limits.
- D . Metrics and charts such as cumulative flow, scatterplot, and work item aging.
- E . All of the above.
True or False: Overall efficiency will automatically increase when you reduce batch size.
- A . TRUE
- B . FALSE
What best describes an eight day 85% Service Level Expectation (SLE)? (choose the best answer)
- A . 85% of all Product Backlog items are completed with 8 days remaining.
- B . At least 85% of all Product Backlog items finished within 8 days.
- C . The team expects a work item to be 85% complete by the end of 8 days of when they start the item.
- D . The team expects they will complete a work item within 8 days of starting on it, 85% of the time.
Which is the most appropriate metric to look at if you want to determine when an item that that has NOT started might be finished?
- A . Historical Cycle Times.
- B . Team Velocity.
- C . Work Item Age.
- D . Team Capacity.
- E . There is no such metric.
True or False: The Scrum Master is responsible for setting the WIP Limits.
- A . TRUE
- B . FALSE
True or False: A Scrum Team’s future output can be determined with Little’s Law.
- A . TRUE
- B . FALSE
True or False: Scrum events can be further enhanced by applying flow-based practices.
- A . TRUE
- B . FALSE