Question #51
When does the System Demo happen?
- A . After the Solution Demo, but before PI Planning.
- B . After every Iteration.
- C . On demand.
- D . After continuous integration.
- E . After Pre-PI Planning.
Question #52
You are invited to help an Agile Release Train that has struggled through multiple PIs. They just finished the second Iteration in the current PI and have nothing to demonstrate at the System Demo.
Program stakeholders are really concerned.
What would you do?
- A . Have every team demonstrate their team increment to the stakeholders separately in the team branch.
- B . Find a vendor that specializes in integrating system increments form multiple teams.
- C . Stop working on any new functionality and fully integrate and test the system; adjust scope based on learnings.
- D . Re-plan the current PI: De-scope to leave enough time to integrate what you’ve built during the IP Iteration.
- E . Re-architect the system so that there are no dependencies between the teams and integration is not needed.
Question #53
AFe assumes that programs commit to the key priorities within the current PI and provide a forecast for a few subsequent PIs.
- A . True
- B . False
Question #54
Iteration Goals have business value assigned by the Product Owner.
- A . True
- B . False