Scaled Agile SAFe-SPC Practice Exams
Last updated on Oct 21,2026- Exam Code: SAFe-SPC
- Exam Name: SAFe Practice Consultant SPC (6.0)
- Certification Provider: Scaled Agile
- Latest update: Oct 21,2026
You organization decided to thoroughly implement the SAFe Principle "Assume variability; preserve options."
What is the optimum path for success?
- A . Assume variability of scope and preserve options for the release date.
- B . Preserve flexibility in system functionality and design, but have fixed Solution intent.
- C . Assume variability of scope, but have fixed Solution Context.
- D . Preserve flexibility in both system functionality and design.
SAFe uses Story points for estimating the size of Stories, Features, Capabilities, and Epics.
- A . True
- B . False
An Agile Release Train prepares for PI Planning. They have both Features and Program Epics among the desirable items for this PI. However, Product Management is stuck because some Epics are too big and won’t fit in this PI.
- A . Pick only those Epics that have clearly defined success criteria and might fit into the PI.
- B . Split Epics into Features and prioritize the Features to determine what should go into the PI.
- C . Split Epics into Features and use capacity allocation to determine what should go into the PI.
- D . Instead of planning just the upcoming PI, plan for a longer period to cover the full duration of the Program Epics.
What are the benefits of cadence and synchronization? (select 2)
- A . Synchronization enables multiple perspectives to be understood, resolved, and integrated at the same time.
- B . They enable systems builders to operate reliably and with certainty within a safety buffer.
- C . Synchronization enables reduction in WIP.
- D . Cadence limits variance.
- E . Cadence enables variability and makes wait times predictable.
The User Experience (UX) team does not believe in Agile development. They say, "We have to understand the full behavior of the eventual system in order to be able to define an effective user experience. We don’t work in timeboxes.
How would you respond?
- A . User experience is indeed a different concept and the team should be exempt from working in Iterations.
- B . Just like system architecture, the entire user experience should be fully designed before an implementation.
- C . Since the team is working in timeboxes, this has been proven to be the most effective way to implement the user experience.
- D . It’s important to have an overall user experience vision before implementation, but the vision can be implemented iteratively for early feedback.
What does innovation accounting mean?
- A . Capitalizing the cost of software development using Story points.
- B . Defining, empirically measuring, and communicating the true progress of innovation.
- C . Demoing Stories that come out of the IP Iteration.
- D . Being sure to account for the investment in new product initiatives on a P&L.
When is the Solution Demo conducted?
- A . On demand.
- B . At the end of each Sprint.
- C . At the end of each PI.
- D . Mid-PI.
What is the target percentage for the Program Predictability Measure?
- A . <50%
- B . 50-75%
- C . 80-100%
- D . 100%
- E . None of the above.