Which activities can the technician perform with the Report and Repair Malfunction SAPUI5 app?
Note: There are 2 correct answers to this question
- A . Schedule
• Dispatch - B . Release
• Print - C . Complete
• Close Report - D . Release
• Start Work
C D
Explanation:
The Report and Repair Malfunction SAPUI5 app is a Fiori app that allows the technician to easily report that a technical object has a malfunction, plan the required repair work, as well as document and confirm the maintenance work when it’s done1.
With this app, the technician can perform the following activities:
C. Complete and Close Report. This is true because the technician can provide information about the malfunction and the job, confirm the job, and close the malfunction report. The technician can also attach pictures or descriptions of the damage, as well as a URL to provide further information about the technical object or the damage1.
D. Release and Start Work. This is true because the technician can release the malfunction report and start working on the job assigned to them. The technician can also view the details of the technical object, the history of recent repair work, the required spare parts, and the work centers involved1.
The technician cannot perform the following activities with this app:
Which functions are available in the Resource Scheduling for Maintenance Planners app? Note: There are 2 correct answers to this question.
- A . Schedule and dispatch maintenance operations by shifts.
- B . Dispatch maintenance order operations
- C . Monitor maintenance order operations due in the next 4 weeks
- D . Print job papers from a maintenance order.
B C
Explanation:
The Resource Scheduling for Maintenance Planners app allows you to monitor important KPIs for your work centers, such as utilization, priority of due maintenance orders, and unconfirmed maintenance orders. You can also use filters to show the information that you are interested in. By clicking a card, you can access the Manage Work Center Utilization app, where you can dispatch maintenance order operations to your work centers. You cannot schedule and dispatch maintenance operations by shifts or print job papers from a maintenance order in this app. These functions are available in other apps, such as the Maintenance Scheduling Board app and the Print Job Papers app.
Reference: Resource Scheduling for Maintenance Planners | SAP Help Portal and Resource Scheduling for Maintenance Planners | SAP Blogs
What are characteristics of the Preparation and Scheduling phase within phase-based maintenance? Note: There are 2 correct answers to this question
- A . If you use the Resource Scheduling apps, you always dispatch orders and operations.
- B . The order moves to the Preparation phase once it is approved and released
- C . Maintenance Planning Buckets give you a list of non-approved notifications
- D . The configuration of the order type decides whether you use Resource Scheduling or not.
B D
Explanation:
The Preparation and Scheduling phase within phase-based maintenance is the phase where the maintenance planner divides the maintenance effort into manageable groups, levels out the workload over several weeks, determines the concrete time period for the requested maintenance work, and checks the availability of all the resources, spare parts and services needed1.
Option B (The order moves to the Preparation phase once it is approved and released) is correct, because the approval and release of the order is the last step of the previous phase (Approval phase)2. Once the order is approved and released, it is ready for preparation and scheduling.
Option D (The configuration of the order type decides whether you use Resource Scheduling or not) is also correct, because the order type determines whether the order is relevant for resource scheduling or not2. Resource scheduling is an optional step in the Preparation and Scheduling phase, where the planner can assign and dispatch the orders and operations to the technicians using the Resource Scheduling apps2.
Option A (If you use the Resource Scheduling apps, you always dispatch orders and operations) is incorrect, because the Resource Scheduling apps allow the planner to either dispatch or assign the orders and operations2. Dispatching means that the planner assigns a specific technician and a specific time slot for the order or operation, while assigning means that the planner assigns only a technician or a team, but not a specific time slot2.
Option C (Maintenance Planning Buckets give you a list of non-approved notifications) is also incorrect, because the Maintenance Planning Buckets app gives the planner a list of approved and released orders that are ready for preparation and scheduling2. The non-approved notifications are handled in the previous phase (Screening phase)2.
Reference: Phase Model for the Maintenance Process
New Phase Model for the Maintenance Processes in S/4HANA Cloud Explaining the Phase-based Process Maintenance Process Phases
In which maintenance object can you use an activity type? Note: There are 2 correct answers to this question.
- A . Maintenance order header
- B . Notification activity
- C . Maintenance order operation
- D . Work center
A C
Explanation:
Maintenance activity type is a key for the type of maintenance activity provided, such as repairs, shutdowns, regular activities, inspections, and so on. It is used to classify data according to the type of maintenance activity in cost evaluations, for example, total costs or number of orders for each technical object1.
Maintenance activity type can be used in the maintenance order header and the maintenance order operation. In the maintenance order header, it is used to specify the overall type of maintenance activity for the order. In the maintenance order operation, it is used to specify the type of maintenance activity for each operation within the order. The maintenance activity type in the operation can be different from the one in the header2.
Maintenance activity type cannot be used in the notification activity or the work center. Notification activity is a key for the type of activity performed in response to a notification, such as inspection, repair, or preventive maintenance. It is not related to the maintenance activity type. Work center is a key for the location where an operation is performed, such as a workshop, a laboratory, or a machine. It is also not related to the maintenance activity type.
Reference: 1: maintenance activity type (PM) (SAP Library – Glossary) 2: maintenance activity type in SAP – Everything you need to know: notification activity (PM) (SAP Library – Glossary) : work center (SAP Library – Glossary)
Which steps support the maintenance technician in the Report and Repair Malfunction app (3 tiles)? Note: There are 3 correct answers to this question
- A . Plan repair work for the responsible work center
- B . Assign a production resource tool (PRT) to the operation
- C . Complete the malfunction report
- D . Verify planned and actual costs
- E . Find malfunction records already created in a list
A C E
Explanation:
The Report and Repair Malfunction app supports the maintenance technician in the following steps: Plan repair work for the responsible work center: The app allows the technician to assign the work items to the work center that is responsible for the repair work. The work center can be a person, a group of persons
Which are the prerequisites for Inspection Checklist Processing? Note: There are 2 correct answers to this question
- A . QM inspection plan with assigned inspection characteristics
- B . Inspection point type assigned to the task list header
- C . Master inspection characteristics assigned to PM task list operations
- D . Classification data assigned to a technical object
A D
Explanation:
This is required to define the inspection scope and the checklist type for the technical object. The inspection plan must be classified with the same class as the technical object and have matching characteristic values1.
Classification data assigned to a technical object: This is required to identify the relevant inspection plan and checklist type for the technical object. The technical object must be classified with the same class as the inspection plan and have matching characteristic values1. The other options are not correct because:
Inspection point type assigned to the task list header: This is not a prerequisite for inspection checklist processing, but an optional setting that allows the user to define inspection points for the checklist items2.
Master inspection characteristics assigned to PM task list operations: This is not a prerequisite for inspection checklist processing, but an optional setting that allows the user to use master inspection characteristics as checklist items2.
Reference: 1: Explaining Inspection Checklists – SAP Learning 2: Generating Inspection Checklists | SAP Help Portal
The planner adds stock materials in the maintenance order.
What are possible options for handling of reservations within a maintenance order? Note: There are 2 correct answers to this question
- A . Open reservations can be cleared when a maintenance order operation is finally confirmed.
- B . Reservations are created only after a material availability check has been performed
- C . For the combination of order type and planner group, you can decide when reservations are created
- D . All open reservations are closed when the maintenance order is set to TECO.
The planner adds non-stock material in a released maintenance order.
What are possible options within the maintenance order? Note: There are 3 correct answers to this question?
- A . A purchase requisition can be created automatically as soon as the order is saved.
- B . The maintenance order can be set to TECO before the invoice is created
- C . A goods receipt can be posted after the maintenance order is technically completed.
- D . A purchase order is created automatically as soon as the order is saved.
- E . A purchase requisition will ALWAYS be created as soon as the order is saved.
A B C
Explanation:
Non-stock materials are materials that are not kept in stock, but are procured externally as required1. They can be maintained in the material master as service products (product type SERV). You can add non-stock materials to an operation or suboperation as a component. The system creates a purchase requisition and a purchase order in the same way as for non-stock materials that you procure externally1.
Among the given options, the following are possible for non-stock materials in a released maintenance order:
A purchase requisition can be created automatically as soon as the order is saved. This is the default behavior for non-stock materials, unless you change the configuration settings2.
The maintenance order can be set to TECO (technically completed) before the invoice is created. This is possible if you use the compatibility mode for external procurement, which allows you to technically complete the order even if there are open purchase requisitions or purchase orders2.
A goods receipt can be posted after the maintenance order is technically completed. This is possible if you use the enhanced mode for external procurement, which allows you to post goods receipts for non-stock materials after the order is technically completed2.
The following options are not possible for non-stock materials in a released maintenance order: A purchase order is created automatically as soon as the order is saved. This is not possible, as the purchase order requires manual processing and approval after the purchase requisition is created2. A purchase requisition will ALWAYS be created as soon as the order is saved. This is not always true, as you can change the configuration settings to create the purchase requisition manually or at a later point in time2.
Therefore, the correct answers are A, B, and C.
Reference: 1: What’s New in SAP S/4HANA 2021 – SAP Online Help 2: How to Configure SAP S/4HANA Asset Maintenance Subcontracting – SAP PRESS
What is the goal of embedded analytics in SAP S/4HANA?
- A . To integrate BW Data Store Objects
- B . To combine transactional and analytical processing
- C . To allow both tactical and strategic analyses within the S/4HANA core
- D . To integrate BW Info Cubes
B
Explanation:
The goal of embedded analytics in SAP S/4HANA is to combine transactional and analytical processing in the same system. Embedded analytics enables real-time operational reporting and decision support within the SAP S/4HANA applications, without the need for data replication or separate data warehouses. Embedded analytics uses the SAP HANA platform capabilities, such as in-memory computing, columnar storage, and calculation views, to provide high-performance and flexible data access. Embedded analytics also leverages the SAP Fiori user interface and the SAP Analytics Cloud to deliver a rich and interactive user experience with predefined and custom analytical apps, dashboards, KPIs, and stories123.
The other options are incorrect because:
Embedded analytics does not integrate BW Data Store Objects or BW Info Cubes. These are data structures that are used in SAP Business Warehouse, a separate analytical system that can be connected to SAP S/4HANA, but not embedded within it4.
Embedded analytics does not allow both tactical and strategic analyses within the S/4HANA core. Tactical and strategic analyses are typically performed on historical and aggregated data that may come from multiple sources, not just the S/4HANA core. For these types of analyses, SAP S/4HANA can be integrated with SAP Analytics Cloud or SAP BW/4HANA, which provide more advanced and comprehensive analytical capabilities.
Which default object type do you use to settle a refurbishment order?
- A . The cost center
- B . The WBS element
- C . The fixed asset
- D . The material