HOTSPOT
A company uses Dynamics 365 Supply Chain Management.
The company wants to use the distributed hybrid topology model to alleviate performance issues at some of its distribution centers. The company has a manufacturing plant, Plant A, which resides at the same physical location as the company home office in Frankfurt, Germany.
The company has the following distribution locations:
• Distribution1 covers Scotland.
• Distribution2 covers Ireland.
• Distribution3 covers the United Kingdom.
• Distribution4 covers Belgium, Germany, and the Netherlands.
• Distribution5 covers the Shetland Islands.
All distribution warehouses use Dynamics 365 Supply Chain Management to receive and distribute goods from Plant A.
Warehouse personnel use the warehouse app to perform their job functions. Because of their proximity to each other, Distribution1, 2, and 3 are managed together and frequently transfer goods between each location.
Due to several connection issues with Dynamics 365 Supply Chain Management, the Shetland Islands location struggles to perform tasks.
The company must maintain as little of its own IT infrastructure as possible, especially in remote areas, but still support daily activities at all locations.
You need to recommend the appropriate topology configuration.
Which type of scaled unit should you use? To answer, select the appropriate options in the answer area.

A company uses Process manufacturing for most products and Discrete manufacturing for other products. The company is creating a formula for a new product. The new item will be used to make a name brand product and two generic brand products. This item has the following requirements:
Production of the name brand and generic products must use the same formula.
The company must produce all three items at the same time.
You need to create a produced item that can make two generic items and one main item.
How should you set up the item?
- A . Create the name brand item as a Bills of material production type item.
Add the two generic items on the Bills of material for the name brand product and use line type phantom. - B . Create the name brand item as a formula planning production of type formula.
Create the two generic items as a formula planning production of type formula.
Copy the formula from the name brand item into each of the generic items. - C . Create the name brand item as a Bills of material production type item.
Create the two generic items as a sub-assembly on the Bills of materials for the name brand product. - D . Create a product as the main product and use a planning item production type.
Create the name brand and two generic products as co-products for the planning item.
A company that makes artisan chocolate is implementing Dynamics 365 Supply Chain Management.
To safeguard the quality of its ingredients, the company limits recipe substitutions of its chocolates.
Its top-selling chocolate bar must contain 20 percent sugar. The sugar can be obtained from either cane or beet sugar depending on supply at the time of production.
The system must be able to automatically substitute the appropriate sugar items when generating production orders to meet the quality level of sugar even when the preferred concentration of cane sugar is out of stock. You need to configure the system.
Which three components must you configure? Each correct answer presents part of the solution. NOTE: Each correct selection is worth one point.
- A . Formula lines
- B . Priority
- C . Item allocation key
- D . Plan group
- E . Item model group
- F . BOM lines
A customer produces light projection toys for holiday decorations throughout the year.
You are in the first month of a season. Production flows take one day to complete.
The floor supervisor reports that seasonal production targets will not be met. You review the Kanban schedule board and identify thousands of unplanned jobs.
You need to plan the jobs to be completed two weeks prior to the start of the next season.
What are two possible ways to achieve this goal? Each correct answer presents a complete solution. NOTE: Each correct selection is worth one point.
- A . Set the Automatic planning option for each unscheduled job to Yes.
- B . Manually schedule each unscheduled job forward from the date of the end of the season.
- C . Manually schedule each unscheduled job to the previous period of the end of the next season.
- D . Set the Automatic planning option for each unscheduled job to No.
- E . Manually schedule each unscheduled job on its due date.
- F . Manually schedule each unscheduled job to the next period of the start of the next season.
A customer produces light projection toys for holiday decorations throughout the year.
You are in the first month of a season. Production flows take one day to complete.
The floor supervisor reports that seasonal production targets will not be met. You review the Kanban schedule board and identify thousands of unplanned jobs.
You need to plan the jobs to be completed two weeks prior to the start of the next season.
What are two possible ways to achieve this goal? Each correct answer presents a complete solution. NOTE: Each correct selection is worth one point.
- A . Set the Automatic planning option for each unscheduled job to Yes.
- B . Manually schedule each unscheduled job forward from the date of the end of the season.
- C . Manually schedule each unscheduled job to the previous period of the end of the next season.
- D . Set the Automatic planning option for each unscheduled job to No.
- E . Manually schedule each unscheduled job on its due date.
- F . Manually schedule each unscheduled job to the next period of the start of the next season.
You maintain responsible resource calendars and production orders for a manufacturing company. All production resources use the same production calendar.
A machine in the facility is defective and must be closed for repairs for the next two days.
You need to configure the resource calendar to close the resource for production for the next two days.
What should you do?
- A . Navigate to the resource. Configure a calendar deviation to set the calendar to closed for the next two days.
- B . Navigate to the calendar used for production and close the next two days.
- C . Navigate to the resource. Change the calendar to closed on the resource.
- D . Navigate to the resource group. Change the calendar to closed on the resource group.
A manufacturing plant uses Lean manufacturing. Operators process Kanban consumption manually by using a mobile device.
The production team must use automatic empty registration for some of the event Kanbans. Registration must occur when the last job of a Kanban is completed.
You need to update the Kanban rule to meet this requirement.
What Kanban setting should you update?
- A . Select to register as empty when handling units are received.
- B . Select to manually register as empty.
- C . Set a fixed Kanban quantity.
- D . Select to register as empty when the source requirement is registered.
DRAG DROP
A manufacturer uses route operations and job scheduling. You use a unique calendar for a conveyor line.
The company observes a decrease in the number of hours a conveyor line resource is operational due to breakdowns. You must make a temporary change to the number of hours the resource is available.
You need to adjust the efficiency percentage for the conveyor line calendar.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

DRAG DROP
A recreational vehicle (RV) manufacturing company is implementing Dynamics 365 Supply Chain Management. All RVs are configured to order.
Quality checks show that there is an issue with the sealant used with the windows in some of the RVs.
You need to identify which RV models use the sealant and change the sealant item.
Which function should you use for each requirement? To answer, drag the appropriate functions to the correct requirements. Each function may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content. NOTE: Each correct selection is worth one point.

DRAG DROP
A recreational vehicle (RV) manufacturing company is implementing Dynamics 365 Supply Chain Management. All RVs are configured to order.
Quality checks show that there is an issue with the sealant used with the windows in some of the RVs.
You need to identify which RV models use the sealant and change the sealant item.
Which function should you use for each requirement? To answer, drag the appropriate functions to the correct requirements. Each function may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content. NOTE: Each correct selection is worth one point.