DRAG DROP
You are the product manager at a distribution company. You are responsible for managing product compliance standards and reporting.
Chemical product, C0001 can be sold in all parts of the United States except for the state of California.
You need to set up these compliance requirements for C0001.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

HOTSPOT
A distribution company implementing Dynamics 365 Supply Chain Management has two warehouses.
One item is purchased and stocked in only Warehouse1. Occasionally, Warehouse2 requires this item based on customer demand. When this occurs, an order for the item must be automatically created for Warehouse2.
You need to configure the automation of the order for Warehouse2.
What should you configure? To answer, select the appropriate options in the answer area. NOTE: Each correct selection is worth one point.

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A company is implementing inventory management in Dynamics 365 for Finance and Operations.
The company needs to block inventory and ensure that physical inventory will not be reserved by other outbound transactions.
You need to select the appropriate option to block the inventory in the system.
Solution: Select the full blocking option in the item sampling page.
Does the solution meet the goal?
- A . Yes
- B . No
A company uses Dynamics 365 for Finance and Operations.
A customer returns a product that is defective for a replacement.
You need to process the return order.
Which three actions should you perform? Each correct answer presents part of the solution. NOTE: Each correct selection is worth one point.
- A . Create a return of type Credit Only
- B . Set the deadline date according to the company policy
- C . Create a credit note for the replaced product
- D . Set the delivery address to the customer’s address in the return order
- E . Create a return of type Physical Return
- F . Set the deadline date to the date the customer returns the defective product
- G . Set the delivery address to the company warehouse in the return order
A single master plan is run with no filters applied.
Buyer1 is reviewing and approving planned orders that were created by Planning Optimization.
Buyer2 runs the same master plan again while Buyer1 is still reviewing planned orders.
What are the two outcomes on Buyer1’s planned orders? Each correct answer presents a complete solution. Select all answers that apply.
- A . Approved planned orders remain unchanged.
- B . Approved planned orders recalculate.
- C . Completed planned orders remain unchanged.
- D . Completed planned orders recalculate.
- E . Unprocessed orders do not recalculate.
DRAG DROP
You need to configure quality controls.
Which solution objects should you configure? To answer, drag the appropriate solution objects to the correct configurations. Each solution object may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content. NOTE: Each correct selection is worth one point.

You need to process the expedited photocopier replacement.
What should you do?
- A . Release the order to the warehouse for shipping.
- B . Create and release a load for the order.
- C . Send the shipment to the warehouse before sending it to the customer.
- D . Create an advance exchange order.
A company is implementing Dynamics 365 Supply Chain Management in one legal entity that contains Sitel1 and Site2.
ItemA is a configured item with configurations ConfigA and ConfigB. The business decides to stop buying ItemA ConfigB into Site2 but will still it at Site’.
You must configure ItemA to ensure the buying rules are implemented
What should you configure?
- A . Variant group
- B . Variant suggestions
- C . Default order rules
- D . Select product variants to release
SIMULATION
You are a functional consultant for a company named Contoso Entertainment System USA (USMF).
You need to regenerate a master plan named DynPlan for item number D0023.
To complete this task, sign in to Dynamics 365 portal.
SIMULATION
You are a functional consultant for a company named Contoso Entertainment System USA (USMF).
You need to regenerate a master plan named DynPlan for item number D0023.
To complete this task, sign in to Dynamics 365 portal.