A business analyst (BA) has documented the components of an information technology (IT) library, in preparation for establishing a consolidated catalogue of IT services. When interviewed, several of the IT managers indicated they already have a catalogue, and have no additional information to provide.
What activity is necessary to support the project?
- A . Analyze existing catalogues
- B . Confirm the project objectives
- C . Expand the interview list
- D . Conduct a focus group
A senior business analyst (BA) is tasked with verifying a set of requirements written by a junior BA for a system. During this exercise, the junior BA will ensure that the requirements exhibit atomic characteristics.
The senior BA will be verifying that the requirements:
- A . can be understood independently of other requirements.
- B . are written using terminology common for the audience.
- C . contain no extraneous and unnecessary content.
- D . are aligned with the identified need of the stakeholders.
A business analyst is meeting with the customer of the project. The customer tells the business analyst that she can only allow the budget of $575,000 for the project. This budget is best described as what type of constraint?
- A . Technical constraint
- B . Verified constraint
- C . Financial constraint
- D . Business constraint
You are a business analyst for your organization and you’re working with the stakeholders to identify the primary inputs to the business analysis approach.
Which of the following are primary inputs of planning the business analysis approach? Each correct answer represents a complete solution.
- A . Organizational process assets
- B . Penalty of not seizing the opportunity
- C . Expert Judgement
- D . Business need
You have been assigned as the Project Manager for a new project that involves the development of a new interface for your existing time management system. You would like to plan the communications that need to be made during the project lifecycle.
Which of the following would be a critical tool/technique to help in your communications planning?
- A . RAM Chart
- B . Affinity Diagram
- C . Stakeholder Analysis
- D . Text-Oriented Chart
You are the business analyst for your organization and you are working with Bill on creating a model. Bill is a little confused about all the different things a model can do for the stakeholders.
You explain to Bill that a model can do all of the following except for which one?
- A . Define the risk and reward for the requirements
- B . Categorize and create hierarchies of items
- C . Define boundaries for business domains
- D . Show business logic
One of the techniques to assess capabilities in an organization is to use SWOT.
What does SWOT accomplish?
- A . SWOT reviews your strengths, weaknesses, opportunities, and threats.
- B . It identifies how current capabilities match up against the influencing factors.
- C . It assesses the strength, weaknesses, opportunities, and threats.
- D . SWOT is a goal setting technique that means "Sweat Works Over Time."
A business analyst (BA) elicits requirements from end users for a new application and then documents a set of use cases and use case scenarios.
What should the BA do next?
- A . Create acceptance and evaluation criteria
- B . Review the use case scenarios
- C . Identify all the roles and responsibilities
- D . Conduct a requirements workshop
Which one of the following is not an event-based elicitation technique?
- A . Focus group
- B . Interface analysis
- C . Interview
- D . Workshop
You are a business analyst for your organization and you’re working with the stakeholders to identify the primary inputs to the business analysis approach.
Which one of the following is a primary input to the business analysis approach?
- A . The business analysis approach will be shaped by the problem or opportunity faced by the
organization. - B . The business analysis approach will be shaped by the penalty of not seizing the opportunity.
- C . The business analysis approach will be shaped by the time allowed for business analysis planning.
- D . The business analysis approach will be shaped by the risks faced by the organization.