What does the decomposition of activities and tasks based on the work breakdown structure create
for the business analyst?
- A . Activity list
- B . Business analysis plan
- C . Network diagram
- D . Project management plan
Several user groups are impacted by a proposed change to their daily work flow.
How should the business analyst (BA) convey these changes so that the user groups understand the impact?
- A . Develop a data model diagram
- B . Create business process models
- C . Write functional requirements
- D . Establish a communication plan
A business analyst wants to elicit requirements from a large group of stakeholders. One of her primary goals of this event is to produce a broad set of options for solutions.
Which elicitation technique would you recommend for this business analyst?
- A . Business rules analysis
- B . Brainstorming
- C . Benchmarking
- D . Data flow diagrams
You are the business analyst for your organization and you’re working with Adam on business analysis processes. Adam is steeped in knowledge regarding the project’s purpose.
Of the following, what type of business analysis stakeholder is Adam?
- A . Project manager
- B . Domain subject matter expert
- C . Sponsor
- D . Regulator
What elicitation technique is best described as a study to compare the strengths and weaknesses of an organization against its peers and competitors?
- A . Brainstorming
- B . Market analysis
- C . Comparative analysis
- D . Benchmarking
You are the business analyst for your organization and you’re working with several stakeholders to identify, manage, and approve requirements. Your organization requires using a plan-driven approach to business analysis and changing management.
In this approach, who is most likely to approve changes to requirements?
- A . Change control board
- B . Requirements owner
- C . Project sponsor
- D . Project manager
A senior manager wants to know at what stage the business analyst (BA) is with the requirements management process. The BA immediately sends a 100-page document with models and business rules to all stakeholders.
Which best practice did the BA violate in this situation?
- A . The distribution included all project stakeholders.
- B . The communication method was inappropriate.
- C . The business rules were included.
- D . The models were included.
A domain subject matter expert (SME) describes a scenario to the business analyst (BA) that may need to be considered for an impending change. The BA and domain SME sketch out the process model for this exception scenario for consideration.
What action does the BA take?
- A . Document the elicitation results then verify and validate them in a requirements review
- B . Plan an observation activity to gain a hands-on understanding of the situation
- C . Review the issue with stakeholders during a follow-up session
- D . Capture and integrate this process model into other appropriate planned outcomes
A business owner has identified a high priority requirement that needs to be implemented immediately. The project manager has asked the business analyst (BA) to perform an impact analysis of this change.
Which factor will the BA need to consider?
- A . Number of systems being affected by the requirement
- B . Original source of the requirement
- C . Method of requirement communication
- D . Selection of the elicitation for the requirement
You are working with several business analysts to determine the solution approach for an identified problem.
All of the following techniques are acceptable for identifying the solution approach except for which one?
- A . Benchmarking
- B . Brainstorming
- C . Decision analysis
- D . Risk analysis