Which of the following descriptions about CU/DU division is incorrect?
- A . The transmission between CU and DU is called backhaul
- B . 5G latency is critical. If the BBU/RRU architecture is used, the C-RAN range is small and deployment is limited.
- C . In the 5G phase, BBU is split into CU and DU. Functions with strict latency requirements are placed in DU. DU needs to be as close to AAU as possible.
- D . The latency-insensitive processing part is placed in the CU, so that the CU can be placed in an appropriately high network position to improve the coordination capabilities and resource sharing between base stations
The PDU session establishment request in 5G must be actively triggered by the UE side.
- A . True
- B . False
What timers may be carried in the SIB1 message of 5G? (Multiple choice)
- A . T304
- B . T301
- C . T300
- D . T380
Which of the following scenarios may report carrier aggregation capabilities? (Multiple choice)
- A . Reconstruction
- B . Re-election
- C . Initial Access
- D . Switch in
Which of the following descriptions of 5QI types is correct?
- A . Added Averaging Window for Non-GBR
- B . URLLC service recommended GBR type 5QI
- C . Standard 5O, a total of 20
- D . Pre-configured 5QI is pre-configured in RAN
Which of the following is wrong in the description of key parameters for frequency priority-based inter-frequency switching?
- A . A4 threshold setting needs to be greater than -90dBm
- B . A1 threshold needs to be greater than A2
- C . The frequency priority frequency switching switch needs to be turned on
- D . The A4 threshold must be greater than the coverage-based A2 threshold set by the target cell.
If the HARQ feedback status of the user’s downlink transmission data is NACK or DTX, it means that the data scheduling fails and the scheduler needs to reschedule the data, that is, perform retransmission scheduling.
- A . True
- B . False
In which messages may the QoS flow configuration information of NR in SA networking be included? (Multiple choice)
- A . Initial UE Message
- B . UE Context Request
- C . PDU Session Resource Setup Request
- D . Initial Context Setup Request
Which of the following descriptions is wrong?
- A . PUCCH short format is suitable for high-frequency scenarios
- B . PUCCH long format is suitable for high-frequency scenarios
- C . The smaller the uplink synchronization timer is set for high-speed scenarios, the better
- D . The larger the uplink synchronization timer is set, the better for high-speed scenarios.
What categories does BWP include? (Multiple choice)
- A . dedicated BWP
- B . default BWP
- C . Initial BWP
- D . Active BWP