During quality analysis, different team members are identifying multiple constraints.
Which of the following tools should the project manager adopt first to help track and prioritize a resolution?
- A . Issue log
- B . Defect log
- C . Risk register
- D . Change log
Which of the following would be the most helpful in providing customers with an application accessible via a web browser?
- A . IaaS
- B . SaaS
- C . PaaS
- D . XaaS
An software engineer is applying new updates to a program in a sandbox environment.
Which of the following risk strategies best describes this practice?
- A . Transfer
- B . Mitigate
- C . Avoid
- D . Accept
During the execution of a project, a project manager wanted to discover how the number of worked hours was affecting the quality of given tasks.
For a two-month period, the following data was documented: Average worked hours
Which of the following describes the result?
- A . A negative correlation exists between the number of mistakes and the working hours.
- B . No correlation exists between the number of mistakes and the working hours.
- C . A low correlation exists between the working hours and the number of mistakes.
- D . A positive correlation exists between the number of mistakes and the working hours.
A project sponsor requires a system that is capable of providing integrated management of all the business’s core functions.
Which of the following systems is the project sponsor describing?
- A . CMS
- B . CRM
- C . EDRMS
- D . ERP
A PM wants to provide a visual representation of how a project is organized into tasks and how the tasks relate to each other.
Which of the following can the PM use?
- A . Milestone chart
- B . Gantt chart
- C . PERT chart
- D . WBS
A project manager was not part of a contract negotiation. The project manager is concerned that stakeholders will expect the project to achieve deliverables requested in the RFP.
Which of the following documents should the project manager produce FIRST to start communication about the boundaries of the project?
- A . Milestone chart
- B . Work breakdown structure
- C . Project charter
- D . Detailed scope statement
After determining the appropriate maintenance window, which of the following should occur NEXT in the operational infrastructure change process?
- A . Implement the change.
- B . Approve the test plan.
- C . Notify customers.
- D . Develop a rollback plan.
Which of the following statements best describes a content management system?
- A . A system to manage electronic signatures and document workflow
- B . A system to manage database integration and provide messaging services
- C . A system to manage shared data on the web, allowing multiple contributors to create, edit, and publish
- D . A system to manage documents archival, such as emails, spreadsheets, and support tickets
A demo presentation for a global project was not as successful as expected because the development team misinterpreted which features needed to be incorporated.
Which of the following has the project manager identified?
- A . Technological factors
- B . Poor sample data
- C . Language barriers
- D . Scope creep