A company is creating a new technology. The company is concerned that the project details could be compromised if a cloud service is used, and another company could launch the technology before the current projected delivery.
Which of the following can the company do to minimize this risk?
- A . Use an on-premises project management scheduling tool.
- B . Limit access to members of the project team.
- C . Mandate overtime to get the project completed sooner.
- D . Ensure all team members have signed a non-disclosure agreement.
Due to multiple changes, the sign-off for the project scope baseline is delayed. The project sponsor has restricted the budget for this project.
Which of the following should the project manager MOST likely do to move forward?
- A . Communicate with the affected stakeholders.
- B . Initiate a formal change request to modify the cost
- C . Adjust the scope to stay within the cost.
- D . Set a new cost using a lightweight estimation method.
Two stakeholders, who have a history of animosity toward one another, are in disagreement during a project. The project’s timeline depends on the stakeholders accomplishing their tasks.
Which of the following conflict resolution methods would be best to utilize?
- A . Smoothing
- B . Confronting
- C . Forcing
- D . Compromising
Which of the following is the main reason for documenting artifacts?
- A . To provide a record of the project’s progress and achievements for future reference
- B . To show stakeholders that the project is on track and progressing as planned
- C . To help team members be aware of roles and responsibilities
- D . To ensure that the project team understands the importance of the project to the organization
A new project has been assigned to a project manager. In order to move forward with the project charter, which of the following should the project manager work with to define the success criteria for the initiative?
- A . Lead architect
- B . Project sponsor
- C . Program manager
- D . Scrum master
A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports.
Which of the following cloud models would the company suggest to the global franchise?
- A . laaS
- B . XaaS
- C . PaaS
- D . SaaS
Two project team members are assigned to set up new work areas and are disagreeing about the placement of hardware and peripherals at the end users’ desks. The requirements do not specify where to place the items, just what is needed in each space.
Which of the following should the project manager do to resolve the conflict?
- A . Send out a survey to the potential end users to gather information about the best functional setup for work productivity.
- B . Provide clear instructions based on personal preference and aesthetics for setup of the work areas.
- C . Explain to team members that the placement of the items is not too important, as long as everything is connected and working.
- D . Facilitate a meeting between team members to review the pros and cons of the different configurations so as to encourage an amicable solution.
A project manager wants to schedule a troubleshooting session for team members who are located in Germany and California.
Which of the following is most important for the project manager to consider when setting up the session?
- A . Cultural differences
- B . Technological factors
- C . Time zones
- D . Language barriers
A project manager is coordinating multiple teams of six people that will each provide feedback for a new product. The teams are recording their opinions, which may be used to define the final product that is sent to mass production.
Which of the following best describes this technique?
- A . Demonstration
- B . Workshop
- C . Brainstorming
- D . Focus group
A PM is working on a strategy to store records.
Which of the following dements must be included in this plan? (Select TWO)
- A . Data management
- B . Issue management
- C . Work breakdown structure
- D . Document management
- E . Communication management
- F . Risk management