A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager.
Which of the following should the project manager do first to prevent this situation from reoccurring?
- A . Meet with the team and highlight the importance of change management.
- B . Roll back the process and submit a change request.
- C . Document the event as a lesson learned.
- D . Remove the team member who bypassed the CCB process.
A project team gathers weekly to review its progress.
Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?
- A . Status report
- B . Project plan
- C . Change log
- D . Meeting minutes
Project team members are leaving the company due to a stressful work environment. The project manager needs to capture this concern about potentially losing team members again.
Which of the following logs should the project manager use?
- A . Risk
- B . Change
- C . Defect
- D . Issue
Before a configuration can be made to a system in development, a document containing information about how the new system will interact with other systems within the organization needs to be written.
Which of the following relationships best describes this scenario?
- A . Start-to-start
- B . Start-to-finish
- C . Finish-to-finish
- D . Finish-to-start
During a staff meeting, a project manager voices a concern about the client billing rate for a particular engineer.
Which of the following documents would the project manager need in order to find this information?
- A . SLA
- B . TOR
- C . SOW
- D . NDA
A program manager is reviewing the project portfolio and prioritizing each project based on the company’s strategic plan.
Which of the following should be considered in this evaluation? (Select TWO).
- A . Company vision
- B . Global environment
- C . Brand value
- D . Mission statement
- E . Portfolio budget
- F . Local legislation
Which of the following is the most important activity for the project manager during the closure of a project?
- A . Obtain project sign-off.
- B . Capture lessons learned.
- C . Document historical information.
- D . Release resources.
Which of the following is a quality assurance tool?
- A . Defining project goals
- B . Identifying the root cause analysis
- C . Assessing employee efficiency
- D . Assessing skill gaps
Government projects require that personnel submit to background screenings for certain clearance requirements.
Which of the following best describes this process?
- A . Data security
- B . Operational security
- C . Physical security
- D . Digital security
Given the following velocity chart:

Which of the following updates on the project status should the Scrum master provide to the senior management team?
- A . The project utilized all of its available reserve.
- B . The project has scope creep.
- C . The project deviated from the critical path.
- D . The project is trending ahead of schedule.