Which of the following are true about the Jira board? (Choose two.)
- A . Only the Scrum board can use ‘Hide completed issues’
- B . Only the Kanban board can use ‘Quick Filters’
- C . Only the Scrum board can use ‘Quick Filters’
- D . Both Kanban and Scrum boards can use ‘Hide completed issues’
- E . Both Kanban and Scrum board can use ‘Quick Filters’
- F . Only the Kanban board can use ‘Hide completed issues’
Which of the following are true about ranking parent issues and sub-tasks? (Choose two.)
- A . Sub-tasks will follow the parent issues’ ranking.
- B . Sub-tasks will have a different rank than the parent issues.
- C . Users need to rank all of the sub-tasks before ranking the parent issue.
- D . Sub-tasks can be ranked in relation to their sibling issues.
Which of the following are part of the Jira Automation rules? (Choose three.)
- A . Listeners
- B . Conditions
- C . Triggers
- D . Actions
- E . Requirements
- F . Steps
Which of the following are true about epic? (Choose two.)
- A . An epic can have another epic. (Epic Link)
- B . An epic cannot have its own issue screen.
- C . An epic cannot convert to a sub-task.
- D . Users need to enable Kanban Backlog to use Epic in the Kanban Board.
- E . Users can customize Epic’s colour in both Kanban and Scrum projects.
- F . An epic can have issues that belong to more than one project.
Given the scenarios below, which project type is suitable for this project?
– Project should be maintained by the project team.
– Users are working on a smaller-scale project.
– Each project should have its own unique configuration.
– Users do not require complex Jira workflow.
– Users’ permissions require minimum maintenance.
Note:
– Company-managed projects are formerly known as classic projects.
– Team-managed projects are formerly known as next-gen projects.
- A . Company-managed project
- B . Team-managed project
Nash is using Kanban boards for his development projects. There are too many issues in the ‘Done’ column in one of the boards. He only wants to see completed issues for the current week.
Which of the following is the best feature that he should use to achieve this?
- A . Board Filter
- B . Swimlanes
- C . Hide completed issues
- D . Quick Filters
- E . Issue Detail View
- F . Board Sub-Filter
A group of developers are working on multiple Jira projects. They can view all Jira projects and have the ‘Move Issues’ permission in all Jira projects. However, they cannot move issues to some of the Jira projects.
What is the possible root cause of this problem?
- A . They do not have the ‘View Issue’ permission in some projects.
- B . They do not have the ‘Transition Issue’ permission in some projects.
- C . They do not have the ‘Edit Issue’ permission in some projects.
- D . They do not have the ‘Create Issue’ permission in some projects.
__________ shows user how their team is progressing against the work for an epic.
Cumulative flow diagram
- A . Epic burndown report
- B . Burndown chart
- C . Velocity chart
- D . Control chart
According to the components below, who will be the assignee if a user created a ticket with all these components?
Project lead: Razi
Project default assignee: Unassigned

- A . Dom
- B . Nina
- C . Razi
- D . Unassigned
- E . Nick
Nash’s team just completed their first sprint.
What can they learn from this chart? (Choose three.)
(Assume Remaining Estimate and Time Spent is enabled for this board.)

- A . Some of the issues are resolved during non-working days.
- B . Some of the issues are still unresolved.
- C . This sprint ends with 0 story points.
- D . This sprint starts with 20 story points.
- E . There are issues worth 5 story points resolved on July 13th.
- F . There are no scope changes in this sprint.